Skip to content

CERC · Central Electricity Regulatory Commission

Renewable Energy Certificates Regulations, 2022 — First Amendment, 2026

Central Electricity Regulatory Commission (Terms and Conditions for Renewable Energy Certificates for Renewable Energy Generation) (First Amendment) Regulations, 2026

Amendment · Gazette copyDated 24 Mar 2026Published in the Gazette 1 Apr 2026F. No. RA-14026(11)/1/2022-CERC dated 24th March, 2026

The Gazette copy of the Renewable Energy Certificates for Renewable Energy Generation (First Amendment) Regulations, 2026.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the First Amendment to CERC's 2022 REC regulations. It is a central, all-India amendment issued on 24 March 2026 and published in the Gazette on 1 April 2026; it comes into force on Gazette publication (p1, p6). The English text begins at p6 after Hindi/Gazette front matter.

It first adds definitions to Regulation 2: Designated Consumer, Renewable Consumption Obligation (RCO) and Virtual Power Purchase Agreement (VPPA), with the latter two tied to the Energy Conservation Act, 2001 and CERC Power Market Regulations, 2021 respectively (p6). It widens Regulation 4 to cover renewable-energy captive/self-consumption plants that do not meet Electricity Rules, 2005 captive conditions (p6).

Regulation 10 is amended so distribution licensees and open access consumers must apply for certificates within three months of State Commission certification of purchases above RPO; no certificate after that period (p6). Regulation 12 is recast to distinguish multipliers for stations commissioned after 05.12.2022 but before the amendment's effect from later stations, which go to Appendix-1; other sources are determined case by case, and an assigned multiplier lasts fifteen years from commissioning, with one certificate per MWh after that if registration continues (p7).

A new Regulation 14A governs VPPA certificates: they transfer to the consumer/designated consumer, may meet RPO/RCO, are extinguished on transfer, and excess certificates can be carried forward but not sold; the Central Agency is to record and extinguish them (pp7–8). Appendix-1 is substituted with principles and scoring for Tariff Range, Technology Maturity and Capacity Credit/Peak Support, with weights and a final multiplier table including a BESS-only note (pp8–9). The Principal Regulations' Gazette publication date is noted (p9).

Standard name
REC Regulations
Primary topics
Renewable energy certificates (REC), Renewable purchase obligation (RPO / RCO), Captive status

Read with this

Other copies of these documents (1)

2 more documents belong here and are not on Voltaic: 1 draft or notice on a draft and 1 draft or notice on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document