Draft Central Electricity Regulatory Commission (Terms and Conditions for Renewable Energy Certificates for Renewable Energy Generation) (First Amendment) Regulations, 2025.

Explanatory memorandum to a draftReleased with the notice dated 22 Sep 2025

Explanatory memorandum to the Renewable Energy Certificates for Renewable Energy Generation Regulations, 2022 — First Amendment, 2025 — Draft.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is CERC's explanatory memorandum for the draft First Amendment to its 2022 REC Regulations, issued for public comment (p1, p10). It explains why the Commission proposes changes and reproduces the proposed amended clauses.

Section 1 sets out the background: the 2022 Principal Regulations came into effect on 5 December 2022; DISCOMs said the three-month post-year deadline for RPO data after State Commission certification was unworkable; stakeholders sought clarity on self-consumption by RE stations that are not captive; the certificate multipliers for RE technologies were due for review after three years; and the Ministry of Power asked CERC, by communication dated 3 March 2025, to create a framework for Virtual Power Purchase Agreements (VPPAs) (p1–2).

Section 2 proposes amending Regulation 4 so that a renewable captive generating station, or a renewable generating plant that does not meet captive criteria but has self-consumption, can be eligible for certificates if it meets the other conditions (p2). Section 3 proposes amending Regulation 10(3) to shift the certificate application window to three months from the date of State Commission certification rather than from the end of the financial year, with no certificate if the application is late (p2–3).

Section 4 reviews the certificate multiplier. It preserves the existing multipliers for stations commissioned after 5 December 2022 but before the amendment takes effect; for later stations, multipliers will come from a new Appendix-1 based on tariff range, technology maturity and capacity credit/peak support, with scores and weights set out in tables (p3–8).

Section 5 inserts Regulation 14A to govern RECs under VPPAs: certificates transfer to the consumer or designated consumer, are used for RPO/RCO compliance, are extinguished, cannot be traded, and excess can be carried forward; the generator must inform the Central Agency and the Central Agency must extinguish and record them (p8–9). Section 6 inserts definitions of Designated Consumer, RCO and VPPA into Regulation 2 (p9). Section 7 asks stakeholders to comment by 23 October 2025 (p10).

Standard name
REC Regulations
Primary topics
Renewable energy certificates (REC), Renewable purchase obligation (RPO / RCO)

Read with this

Other copies of these documents (2)

2 more documents belong here and are not on Voltaic: 1 draft or notice on a draft and 1 draft or notice on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.