Terms and Conditions of Tariff Regulations, 2011 — Third Amendment, 2017 — Draft

West Bengal Electricity Regulatory Commission (Terms and Conditions of Tariff) (Third Amendment) Regulations, 2017

Draft amendmentDated 19 Jul 2017

Draft

A proposal that has since been finalised as the Terms and Conditions of Tariff Regulations, 2011 — Third Amendment, 2020.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on wberc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the West Bengal Electricity Regulatory Commission's draft Third Amendment to its Terms and Conditions of Tariff Regulations, 2011. It works on the machinery of tariff determination — fuel cost, time-of-day definition, payment terms and settlement — rather than on tariff levels. Regulation 1 (p1) gives the title and commencement: in force on publication in the Official Gazette and applying to tariff determination, APR, FCA, FPPCA, MVCA and MFCA for 2017-18 and onwards; the notification number and date are still blanks in this draft.

Regulation 2 (p1–2) inserts coal-mining definitions into Regulation 1.2.1 — Mine Developer and Operator, mine owner, overburden, overburden removal and stripping ratio. Regulation 3 (p2) replaces Regulation 3.13, re-specifying the normal, peak and off-peak time strata for TOD schemes, with a proviso allowing the Commission to fix different strata for a particular licensee or generating station. Regulation 4 (p2–3) replaces Regulation 4.14, restating delayed payment surcharge rates for consumers generally and a separate scale for L&MV agriculture consumers, while preserving the Commission's power to revise the rates by order.

Regulation 5 (p3–10) is the bulk. It substitutes Regulation 5.8 on fuel cost determination: which coal sources may be considered (CIL linkage/e-auction/MoU, indigenous auctions, imports, own overseas mines, and captive mines allotted free of cost or through reverse bidding), the conditions and approvals attached to each, the cost heads eligible for the transfer price, transit and handling loss allowances, limestone, use of alternative fuel and blending, and the FPPCA/MVCA/MFCA fuel-surcharge mechanism with its schedules, publication and reconciliation duties. Regulation 6 (p10) extends the unforeseen exigency fund to energy-efficiency activity with prior approval; Regulation 7 (p10) replaces Regulation 6.5, moving deviation settlement onto CERC frequency-linked rates and renaming UI as Deviation Settlement throughout. Regulation 8 (p10–11) replaces the e-payment rebate provision. Regulations 9–11 (p11–12) touch CVPF in Schedule-1 and the notes and clause (b) of Schedule-7B, substituting CoalGCV for CoalUHV. Regulations 12–13 (p12) modify Schedule-9A paragraphs D and J, and Regulation 14 (p12–13) re-specifies Annexure-C2 TOD tariff schemes for listed consumer classes.

Standard name
Tariff Regulations
Primary topics
Tariff determination, Fuel price and supply, Fuel and power purchase cost adjustment

Read with this

Voltaic last read WBERC's website for final documents on 24 Nov 2026 and for drafts on 21 Nov 2026. A document WBERC issued after the page that lists it was read may not be held by Voltaic yet.