Procedure of verification of status of CGP, 2024
TGERC – Procedure of verification of status of CGP – Approval issued
ProcedureDated 30 Nov 2024Procds. No. / TGERC / E – 711594 / SECY / 78 / 2024 dated 30 .11.2024
Made under the Terms and Conditions of Open Access Regulation, 2024.
Summary
Summary written by software. Check the regulator's original before you rely on it.
The Telangana Electricity Regulatory Commission's proceedings dated 30 November 2024 approve a detailed procedure for verifying whether a generating plant in Telangana and its users genuinely qualify as a captive generating plant (CGP) and captive users. It is made to give effect to clause 7 of the Commission's 'Terms and Conditions of Open Access' Regulations, 2024 (Regulation No. 1 of 2024, notified 18.03.2024) read with Rule 3 of the Electricity Rules, 2005 and its amendments (p1–2).
After setting the objective and applicability (p2), the procedure defines its terms and reproduces the statutory definitions and the Rule 3 captive requirements, including the special-purpose-vehicle illustration (pp2–7). It names the Commission as Verifying Authority, acting on a consolidated report from the distribution licensee (pp7–8). Section 6 states the general conditions to be tested — consumption directly or through an energy storage system, consumption by subsidiary/holding companies, change of ownership, and the ownership and consumption tests for cooperative societies, associations of persons, SPVs, firms and LLPs (pp8–9).
Section 7 lays out the annual cycle: an affidavit and data by 31 May, a distribution-licensee consolidated report by 30 June, clarification powers, assistance from STU/SLDC, and a two-month window for the Commission to determine status; failure to qualify means the plant ceases to be a CGP for that financial year only (pp9–10). Sections 8 and 9 detail ownership verification with the documents and certificates required for each ownership form, and consumption verification, including how network losses, auxiliary consumption and open-access drawal are treated (pp10–16). Section 10 covers default by an individual shareholder, and Section 11 requires interface metering with real-time communication (p16). Schedule-1 is an affidavit format, and Formats I to V (pp19–36) are the certificates and reporting tables to be filed.
Read with this
The regulation
- Dated 15 Mar 2024Terms and Conditions of Open Access Regulation, 2024
Amendments and corrections
Commencement notices and reasons
Other copies of these documents (1)
Proposed changes (drafts with no final yet)
- Released with the notice dated 30 Sep 2024Draft Procedure for Verification of Captive Status of Generating Plants in Telangana
- Dated 30 Sep 2024Public notice: Draft Procedure for Verification of Captive Status of Generating Plants in Telangana — Public Notice
Earlier drafts
- Dated 15 Nov 2025Terms and Conditions of Open Access Regulations, 2024 — First Amendment, 2025 — Draft
- Dated 15 Nov 2025Public notice: Terms and Conditions of Open Access Regulation, 2024 — First Amendment — Public Notice — Draft
One more document belongs here and is not on Voltaic: a draft or notice on a draft.
Voltaic last read TSERC's website for final documents on 24 Nov 2026 and for drafts on 21 Nov 2026. A document TSERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.