In the matter of: 1. Increasing the limit of contract demand (CD) up to 55 MVA from the current limit of 35 MVA under 110 KV supply voltage. 2. Conversion from one type of use to another type of use (Change in tariff Category).
OrderDated 17 Jun 2025
Made under the Conditions of Supply of Electricity of Distribution Licensees in the State of Karnataka, 2006 — with First and Second Amendments.
Summary
Summary written by software. Check the regulator's original before you rely on it.
KERC disposes of two issues through a removal-of-difficulties order dated 17.06.2025 (p1). First, an EHT consumer asked to take 110 kV supply with contract demand above the 35 MVA limit in the Conditions of Supply, and KPTCL sought clarification on sanctioning load beyond 35 MVA on a 110 kV line (p1). Second, at public hearings consumers complained that distribution licensees were forcing new equipment for HT-to-LT conversion instead of allowing existing consumer-installed distribution transformers and LT lines to be reused (p1).
The Commission accepts both. Operatively, it raises the 110 kV contract demand limit to 55 MVA from 35 MVA, subject to technical feasibility — voltage regulation, KPTCL substation power transformer capacity, energy losses, and line loading within thermal rating. For CD above 35 MVA up to 55 MVA, augmentation charges are ₹10 lakhs per MVA (p2). On HT-to-LT conversion, existing distribution transformers, LT service lines and associated equipment/materials installed by the consumer at his cost during HT supply may be used for the LT connection (p2). The Commission directs its office to propose amendments to the relevant CoS/KERC Regulation clauses through the prescribed procedure (p2). No gazette publication or independent commencement date is stated.
Read with this
The regulation
Amendments and corrections
- Dated 14 Mar 2008Conditions of Supply of Electricity of the Distribution Licensees in Karnataka, 2006 — First Amendment, 2008
- Dated 1 Jul 2010Conditions of Supply of Electricity of Distribution Licensees in Karnataka — Second Amendment, 2010
- Dated 25 Aug 2014Karnataka Conditions of Supply of Electricity, 2006 — Third Amendment, 2014
- Dated 25 Jan 2016Conditions of Supply of Electricity of Distribution Licensees in Karnataka — Fourth Amendment, 2016
- Dated 22 Nov 2016Conditions of Supply of Electricity of Distribution Licensees in Karnataka (CoS), 2006 — Fifth Amendment, 2016
- Dated 27 Dec 2017Conditions of Supply of Electricity of Distribution Licensees in Karnataka (CoS), 2006 — Sixth Amendment, 2017
- Dated 26 Dec 2018Conditions of Supply of Electricity of Distribution Licensees in Karnataka (Seventh Amendment), 2018
- Dated 22 Oct 2019Conditions of Supply of Electricity of Distribution Licensees in Karnataka, 2006 — Eighth Amendment, 2019
- Dated 1 Jul 2022Conditions of Supply of Electricity of Distribution Licensees in Karnataka (CoS), 2006 — Tenth Amendment, 2022
3 more documents belong here and are not on Voltaic: 3 copies in another language.
Voltaic last read KERC's website for final documents on 24 Nov 2026 (3 pages) and for drafts on 23 Nov 2026. A document KERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.