OERC · Odisha Electricity Regulatory Commission

Distribution (Conditions of Supply) Code, 2019 — New Connection Timeline Modification Notification, 2024

Notification dated 11.12.2024

NotificationDated 11 Dec 2024OERC-Engg-92/2003 (Vol.VIII) /1448 dated 11.12.2024

Read with the Odisha Distribution (Conditions of Supply) Code, 2019.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on orierc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a one-page OERC notification issued at Bhubaneswar on 11 December 2024, modifying a timeline clause in the OERC Distribution (Conditions of Supply) Code, 2019, and thereby following up on Notification No. 1424 dated 09.12.2024 (p1).

The Commission recalls that it had framed the Code under Section 50 read with Section 181(2) and Part-VI clauses (t), (v), (w) and (x) of the Electricity Act, 2003, published in the Odisha Gazette extraordinary in October 2019 (p1). It then notes that, using Regulation 201 of the Code, it had already issued directions on 09.12.2024 replacing the timelines in Regulation 33 and adding fee-structure provisions in Regulation 22(vi) to align with the Electricity (Rights of Consumers) Rules, 2020 (p1).

This notification continues that exercise by making one textual change to Regulation 33(a). In the prior notification's paragraph 1, the words "seven days in municipal areas" are replaced by "three days in metropolitan areas, seven days in other municipal areas" (p1). The change takes effect from the date the Commission notifies it and remains in force until the Code is further amended (p1).

Standard name
Electricity Supply Code
Primary topics
New connections and load changes, Conditions of supply

Read with this

Voltaic last read OERC's website for final documents between 24 Nov 2026 and 26 Nov 2026 (9 pages) and for drafts on 21 Nov 2026. A document OERC issued after the page that lists it was read may not be held by Voltaic yet.