RE Tariff Regulations, 2023 — First Amendment, 2024 — Statement of Reasons
- 1. "10. Minimum Quantum of electricity to be purchased by …… The Energy Storage Obligation shall be calculated in energy terms as a percentage of total consumption of electricity and shall be treated as fulfilled only when and at least 85% of the total energy storage in the Energy Storage System …
- 1.3. Shri Hardeep Rajput › 2. Commission's view and decision… 11 --> Financial Year Storage 2024-25 1.5% 2025-26 2.0% 2026-27 2.5% 2027-28 3.0% 2028-29 3.5% 2029-30 4.0% (5)The Energy Storage Obligation shall be calculated in energy terms as a percentage of total consumption of electricity …
3 matching passages in this document
RE Tariff Regulations, 2023 — Statement of Reasons
- 1.13 Regulation 10 i.e. Minimum Quantum of electricity to … › Commission's View… shall be solar/wind energy alongwith/through storage Financial Year Storage 2023-24 1.0% 2024-25 1.5% 2025-26 2.0% 2026-27 2.5% 2027-28 3.0% 2028-29 3.5% 2029-30 4.0% (5) …
- 1.13 Regulation 10 i.e. Minimum Quantum of electricity to …Financial Year Storage 2023-24 1.0% 2024-25 1.5% 2025-26 2.0% 2026-27 2.5% 2027-28 3.0% 2028-29 3.5% 2029-30 4.0% (5) …
3 matching passages in this document
RE Tariff and Other Terms for Supply of Electricity (First Amendment) Regulations, 2023
- NOTIFICATION › 2. Amendment in Regulation 9 of the Principal Regulations… The Energy Storage Obligation shall be calculated in energy terms as a percentage of total consumption of electricity and shall be treated as fulfilled only when and at least 85% of the total energy storage in the Energy Storage System …
- NOTIFICATION › 2. Amendment in Regulation 9 of the Principal Regulations… power plants of non-obligated entities for meeting its 'Other RPO' compliance based on the gross energy generated meter reading of such rooftop or small solar power plant. (4) The following percentage of total energy consumed shall be …
3 matching passages in this document
RE and Non-Fossil Fuel Co-generation Tariff Regulations, 2023
2 amendments on Voltaic
- CHAPTER 3 › RENEWABLE PURCHASE OBLIGATION (RPO)… The Energy Storage Obligation shall be calculated in energy terms as a percentage of total consumption of electricity and shall be treated as fulfilled only when and at least 85% of the total energy storage in the Energy Storage System …
- CHAPTER 3 › RENEWABLE PURCHASE OBLIGATION (RPO)… the gross Solar energy generated from the GRPV/GSPV of non-obligated entities for meeting its 'Solar RPO' compliance based on the gross energy generated meter reading of such GRPV/GSPV. (4) The following percentage of total energy …
3 matching passages in this document
RE Tariff Regulations, 2023 — First Amendment, 2024
Amends the RE and Non-Fossil Fuel Co-generation Tariff Regulations, 2023
- UTTARAKHAND ELECTRICITY REGULATORY COMMISSION › 2. Amendment in Regulation 10 of the Principal Regulations… The Energy Storage Obligation shall be calculated in energy terms as a percentage of total consumption of electricity and shall be treated as fulfilled only when and at least 85% of the total energy storage in the Energy Storage System …
- UTTARAKHAND ELECTRICITY REGULATORY COMMISSION › 2. Amendment in Regulation 10 of the Principal Regulations… consumers or consumers with Captive Power Plants shall fulfil their obligation as per the specified total renewable energy target irrespective of the non-fossil fuel source. (2) For the purpose of this RPO framework, for every obligated …
3 matching passages in this document
RE Tariff and Other Terms for Supply of Electricity from Renewable Energy Sources, 2018 — First Amendment, 2023 — Statement of Reasons
- UTTARAKHAND ELECTRICITY REGULATORY COMMISSION › Statement of Reasons… The Energy Storage Obligation shall be calculated in energy terms as a percentage of total consumption of electricity and shall be treated as fulfilled only when and at least 85% of the total energy storage in the Energy Storage System …
- 1.2. UREDA submission › 2. Commission's view and decision… The Energy Storage Obligation shall be calculated in energy terms as a percentage of total consumption of electricity and shall be treated as fulfilled only when and at least 85% of the total energy storage in the Energy Storage System …
3 matching passages in this document
RE Tariff Regulations, 2023 — Second Amendment, 2025 — Statement of Reasons
- UTTARAKHAND ELECTRICITY REGULATORY COMMISSION 'Vidyut … › Statement of Reasons… Thereafter, MoP issued national framework for promoting energy storage system in August 2023. Further, UJVN Ltd. vide its letter dated 16.04.2025 submitted the proposal for its cost data and other performance norms prevalent in other …
- 3.1 UPCL… GoI has issued Guidelines for "Procurement and Utilization of Battery Energy Storage Systems as part of Generation, Transmission and Distribution assets, along with Ancillary Services" on 10.03.2022. Clause 1.1 of Section III i.e. …
3 matching passages in this document
RE Tariff Regulations, 2023 — Second Amendment, 2025
Amends the RE and Non-Fossil Fuel Co-generation Tariff Regulations, 2023
- UTTARAKHAND ELECTRICITY REGULATORY COMMISSION NOTIFICATION › 2. Amendment in Regulation 2 i.e. 'Scope and extent of …… for implementation of Battery Energy Storage System for the discom, the trading margin shall be 5 paise per unit. The L-1 tariff plus a margin of 5 paise shall not exceed the generic tariff determined by the Commission for the year of …
- UTTARAKHAND ELECTRICITY REGULATORY COMMISSION NOTIFICATION › 5. Amendment in sub-regulation (1)(xvi) of Regulations 3, …For a Battery Energy Storage System COD shall mean the date declared by the project developer or the implementing agency, after successful commissioning and performance testing of the system, …