MPERC · Madhya Pradesh Electricity Regulatory Commission

Co-Generation and Generation of Electricity from Renewable Sources of Energy (Revision-II) Regulations, 2021 — First Amendment, 2023

Madhya Pradesh Electricity Regulatory Commission (Co Generation and Generation of Electricity from Renewable Sources of Energy) (Revision-II) Regulations 2021 (First Amendment) [ARG-33(II)(i) of 2023]

AmendmentDated 16 Jan 2023MPERC/2023/160 dated 16th January 2023

Amends the Cogeneration and Generation of Electricity from Renewable Sources of Energy Regulations, 2021 — Revision-II.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on mperc.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the First Amendment to MPERC's 2021 Co-Generation and Generation of Electricity from Renewable Sources of Energy (Revision-II) Regulations. Issued in Bhopal on 16 January 2023 (p1), it extends to the whole of Madhya Pradesh and comes into force on publication in the Madhya Pradesh Gazette; the Gazette date is not printed (p1).

Regulation 2 is rewritten first (p1–2). The amendment inserts 'Entity' — a consumer with contracted demand or sanctioned load of 100 kW or more, except captive consumers, who have no load limit — and a broad 'Green Energy' definition covering renewable energy, hydro, storage and green hydrogen/ammonia. It also recasts 'Obligated Entity' to include distribution licensees, captive users and open access consumers, and updates the definition of a renewable-energy-based captive generating plant.

Regulation 3 is then substantially substituted (p2–5). The amendment sets a financial-year-wise renewable purchase obligation (RPO) trajectory for FY2022-23 to FY2029-30, split into Wind RPO, Hydro Purchase Obligation (HPO), Other RPO and Total RPO (p2). Wind RPO is met from projects commissioned after 31 March 2022 and specified excess older wind; HPO from hydro, pumped storage and small hydro commissioned on or after 8 March 2019 up to 31 March 2030; and Other RPO from any other RE project (p3). It also lays down how free power from hydro projects can be used for HPO, annual true-up, treatment of shortfalls and future notification of the post-2030-31 HPO trajectory (p3–4). An energy storage obligation trajectory from FY2023-24 to FY2029-30 is introduced, with storage counting towards RPO only where the stored energy is renewable (p4).

New Regulations 3.8(A) to 3.8(C) allow any entity, obligated or not, to procure green energy by own generation, open access, discom requisition, captive use, green hydrogen/ammonia purchase or other sources; provide for green certificates from the discom; and allow the Commission to introduce consumer green ratings (p5–7). Finally, Regulation 10.1 on banking of renewable energy is substituted with monthly banking conditions, permitted quantum and no carry-forward, and 'additional surcharge' is omitted from Regulation 11.2(d) (p7).

Standard name
RPO Regulations
Primary topics
Renewable purchase obligation (RPO / RCO), Energy storage obligation, Green energy open access

Read with this

Voltaic last read MPERC's website for final documents between 24 Nov 2026 and 26 Nov 2026 (4 pages). A document MPERC issued after the page that lists it was read may not be held by Voltaic yet.