MPERC · Madhya Pradesh Electricity Regulatory Commission

Cogeneration and Generation of Electricity from Renewable Sources of Energy (Revision-II) Regulations, 2021 — Fourth Amendment, 2025

Madhya Pradesh Electricity Regulatory Commission (Cogeneration and Generation of Electricity from Renewable Sources of Energy (Revision-II) Regulations 2021(Fourth Amendment) [ARG-33(II)(iv) of 2025]

AmendmentDated 4 Mar 2025MPERC/2025/423 dated 04/03/2025

Amends the Cogeneration and Generation of Electricity from Renewable Sources of Energy Regulations, 2021 — Revision-II.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on mperc.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Fourth Amendment to MPERC's 2021 regulations on cogeneration and generation from renewable sources (the "Principal Regulations", RG-33(II) of 2021), issued from Bhopal on 4 March 2025 under s.181 read with s.61(h) and s.86(1)(e) of the Electricity Act 2003 (p1). It extends to the whole of Madhya Pradesh and comes into force from publication in the Madhya Pradesh Gazette — the Gazette date is not printed (p1).

Clauses 2 and 3 do the substantive work on definitions and RPO eligibility. Regulation 2(xi) is simply omitted; 'Open Access Consumer' is broadened to cover consumers availing open access under the CERC GNA Regulations 2022 or MPERC's intra-State open access regulations, including short-term transmission/distribution consumers; 'Renewable Purchase Obligation' and 'State Agency' are redefined; and two new definitions — 'State RPO Monitoring Agency/Agencies' and 'RPO Portal' — are inserted (p1–2). Regulation 3.1.9 is replaced with a revised set of flexibilities allowing shortfalls in the 'Other RPO', Wind RPO and Hydro ('HPO') categories to be offset against excess wind and hydro energy (p2–3).

Clauses 4 to 7 are cross-reference updates, carrying the Principal Regulations onto newer instruments: metering at the generating plant site by the Distribution Licensee and energy accounting by SLDC are tied to the MP Electricity Balancing and Settlement Code 2023, the Grid Code (Revision-III) 2024 and the Distribution Code (Revision-1) 2024, and references to the 2015 net metering regulations are replaced by the Grid Interactive Renewable Energy Systems Regulations [Revision-II] 2024 (p3–4).

Clauses 8 to 11 build the compliance machinery. New Regulations 12.5–12.7 require obligated entities and State RPO Monitoring Agencies to register on the Commission's RPO portal and report monthly, with an annual monitoring report due by 15 May and a Commission order declaring RPO compliance status (p4). Regulation 14 is replaced, covering the State Agency's REC accreditation role and the new monitoring agencies (p5). Regulation 15 is replaced with a fuller default regime — a separate REC purchase fund, regulation of short-term open access, breach of licence conditions for non-deposit within 15 days, penalties under s.142, and case-by-case carry-forward on genuine difficulty (p5–7).

Standard name
RPO Regulations
Primary topics
Renewable purchase obligation (RPO / RCO), Open access, Renewable energy certificates (REC)

Read with this

Voltaic last read MPERC's website for final documents between 24 Nov 2026 and 26 Nov 2026 (4 pages). A document MPERC issued after the page that lists it was read may not be held by Voltaic yet.