MPERC · Madhya Pradesh Electricity Regulatory Commission

Cogeneration and Generation of Electricity from Renewable Sources of Energy (Revision-II) Regulations 2021 — Sixth Amendment, 2026

Madhya Pradesh Electricity Regulatory Commission (Cogeneration and Generation of Electricity from Renewable Sources of Energy) (Revision-II) Regulations 2021 (Sixth Amendment) [ARG-33(II)(vi) of 2026]

AmendmentDated 4 Aug 2026No.1349/MPERC/2026 dated 4th August 2026

Amends the Cogeneration and Generation of Electricity from Renewable Sources of Energy Regulations, 2021 — Revision-II.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on mperc.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Sixth Amendment to MPERC's 2021 regulations on cogeneration and generation of electricity from renewable sources, issued at Bhopal on 4 August 2026 as No.1349/MPERC/2026 and signed by the Commission Secretary (p3). It is a two-clause instrument. Clause 1 supplies the short title, commencement on publication in the Madhya Pradesh Gazette, and territorial extent to the whole State (p3). Clause 2 amends Regulation 3 of the Principal Regulations, 2021 (p3).

The operative change is the insertion of new sub-regulations 3.1.9 to 3.1.12 after Regulation 3.1.8. Together they create an Energy Storage Obligation: a minimum share of total energy procured to be sourced as solar/wind energy together with, or through, storage. The obligation is expressed on an energy basis and rises across four financial years from 2026-27 to 2029-30, given in a small table (p3–4; the same table also appears uncaptioned on p1).

3.1.10 says how it is measured and when it counts as satisfied: as a percentage of total electricity procurement, in energy terms, tied to the minimum renewable share already set by Regulation 3.1; and treated as fulfilled only where at least 85% of the energy stored in the Energy Storage System over a year is procured from renewable sources (p4). 3.1.11 makes the renewable-sourced storage count towards the total RPO under Regulation 3.1 (p4). 3.1.12 makes the obligation subject to periodic review in the light of pumped storage commissioning and operation, new commercially viable storage technologies and falling battery storage costs (p4).

The text supplied is only the operative body plus fragments: page 1 is the obligation table standing alone, and page 2 preserves a single heading line naming BESS, PSP, commissioning and the Energy Storage Obligation, consistent with a contents entry or clause caption rather than operative text. The Gazette date is not printed, so commencement cannot be fixed from the document itself.

Standard name
RPO Regulations
Primary topics
Energy storage obligation, Renewable purchase obligation (RPO / RCO)

Read with this

Voltaic last read MPERC's website for final documents between 24 Nov 2026 and 26 Nov 2026 (4 pages). A document MPERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on mperc.in ↗

Report an issue with this document