CERC · Central Electricity Regulatory Commission
Communication System for inter-State Transmission of Electricity Regulations, 2016 — Public Notice — Draft
Draft Central Electricity Regulatory Commission (Communication System for inter-State transmission of electricity) Regulations, 2016
Public notice on a draftDated 7 Sep 2016No. L-1/210/2016/CERC dated th September, 2016
Draft
The draft has since been finalised as the Communication System for inter-State Transmission of Electricity Regulations, 2017.
Public notice on the Communication System for inter-State Transmission of Electricity Regulations, 2016 — Draft.
Summary
Summary written by software. Check the regulator's original before you rely on it.
The Central Electricity Regulatory Commission (CERC) issued this public notice on 7 September 2016 (p1) to announce the Draft CERC (Communication System for inter-State transmission of electricity) Regulations, 2016. It records that the draft was made under Section 79(1)(c) and (h) read with Section 178 of the Electricity Act, 2003, and that the draft regulations and an explanatory memorandum are annexed and downloadable (p1). Under Section 178(3) and the Electricity (Procedure for Previous Publication) Rules, 2005, it invites suggestions, objections and comments from stakeholders and interested persons, to be sent to the undersigned by 10 October 2016 (p1). It warns that comments received after that date may not be considered while finalising the regulations (p1). The notice is signed by the Secretary, CERC (p1). The notice itself does not set out the draft provisions; those are in the annexed draft and explanatory memorandum (p1).
Read with this
The regulation
Commencement notices and reasons
Procedures and orders made under it
- Dated 19 Jan 2024Procedure on Maintenance and Testing of Communication System under the Communication System for inter-State transmission of electricity Regulations, 2017 — Approval Order, 2024
- Dated 19 Jan 2024Centralized Supervision for Quick Fault Detection and Restoration Procedure, 2024 — Approval Order under Communication System Regulations, 2017
- Dated 19 Jan 2024Guidelines on Availability of Communication System, 2024
- Dated 19 Jan 2024Guidelines on Interfacing Requirements under the Communication System for inter-State Transmission of Electricity Regulations, 2017
Earlier drafts
- Released with the notice dated 7 Sep 2016Communication System for inter-State Transmission of Electricity Regulations, 2016 — Draft
- Released with the notice dated 7 Sep 2016Explanatory memorandum: Draft Communication System for inter-State Transmission of Electricity Regulations, 2016 — Explanatory Memorandum
One more document belongs here and is not on Voltaic: a draft or notice on a draft not held as English text.
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.