Skip to content

TNERC · Tamil Nadu Electricity Regulatory Commission

Grid Connectivity and Intra-State Open Access Regulations, 2012 — Draft

Tamil Nadu Electricity Regulatory Commission (Grid connectivity and Intra-State Open Access) Regulations, 2012

Draft regulationDated 26 Sep 2012TNERC/ISOA/..... dated .....-2012

Draft

A proposal that has since been finalised as the Grid Connectivity and Intra-State Open Access Regulations, 2014.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on tnerc.tn.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a consultation package, not a notified instrument. Page 1 is an explanatory memorandum: a first draft was hosted on 02-06-2011 with comments due 01-07-2011, and after several Commission orders on open access and connectivity the staff reworked it; the updated draft is now on the website for comments until 15-10-2012. Pages 2–3 carry the draft notification, which recites the 2005 Intra-State Open Access Regulations, states that they will be repealed and re-enacted, and gives notice that the new Regulations will be gazetted fifteen days after hosting.

Chapter 1 (pp3–7) sets the title, commencement on Gazette publication, scope over intra-State transmission and distribution systems (including use in conjunction with the inter-State system, subject to SLDC directions and Restriction & Control measures) and the definitions, including the allotted-versus-reserved capacity distinction, the long/medium/short-term duration bands, imbalance and wheeling. Chapter 2 (pp7–15) governs connectivity: who applies to the STU or to the distribution licensee, application fees, the lead-generator agreement requirement where several generators share a connection point, interconnection studies under the CEA connectivity standards, connection and tripartite agreements, testing/infirm power injection before COD, dedicated-line and bay costs, and a 30-day decision window. Chapter 3 (pp15–17) sets eligibility and conditions for open access (dues, insolvency, independent feeders) and when augmentation may be built for long-term versus medium/short-term access.

Chapter 4 (pp17–33) is the procedural core: categories of open access customers, applications for long-term, medium-term and short-term access (inter-State cases routed to CERC rules), bank guarantees, agreements, extension and relinquishment, day-ahead and contingency scheduling, bidding when capacity is congested, consent timelines for distribution licensees with deemed consent, and allotment priority. Chapter 5 (pp33–39) deals with charges — transmission, wheeling, cross-subsidy, additional surcharge, scheduling and system operation, start-up/standby, parallel operation, restoration and residual heads, many left to later Commission determination. Chapters 6–9 (pp39–49) cover scheduling, ABT-compliant metering, revision, transmission and distribution losses, imbalance and reactive energy settlement through a State Imbalance Pool Account, billing and disbursement, late payment, default, payment security, and the open-access information SLDC must publish. Chapter 10 (pp49–51) adapts the consumer procedure to generating stations connected to a distribution system. Chapter 11 (pp51–58) covers relinquishment compensation, capacity-availability computation, curtailment priority, the detailed procedures to be approved within 60 days, grievance redressal, removal of difficulties, force majeure, amendment powers and repeal with savings.

Tables 1 and 2 (pp59–71) lay out, for distribution-connected and transmission-connected consumers respectively, the nodal agency, fee slabs, documents, disposal timelines, charges and losses by location of injection and drawal and by access duration. Formats ST1–ST4 and the payment schedule (pp72–80) supply the application, approval, congestion/bidding invitation and bid templates.

Standard name
Open Access Regulations, Connectivity and GNA Regulations
Primary topics
Open access, Connectivity and GNA, Open access charges

Read with this

Voltaic last read TNERC's website for final documents on 29 Sep 2026 and for drafts on 24 Nov 2026. A document TNERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on tnerc.tn.gov.in ↗

Report an issue with this document