TNERC · Tamil Nadu Electricity Regulatory Commission
Detailed Procedure for Open Access in Transmission and Distribution System
ProcedureDate not stated
Made under the Grid Connectivity and Intra-State Open Access Regulations, 2014.
Summary
Summary written by software, from pages 1 to 41 of 123. Check the regulator's original before you rely on it.
This document is the Detailed Procedure for Open Access in the Transmission and Distribution System of Tamil Nadu, prepared by TN SLDC under Regulation 43 of the TNERC (Grid Connectivity and Intra-State Open Access) Regulations, 2014, and approved by the Commission (p1). It is the operational handbook that turns the 2014 Regulations into step-by-step forms, time limits and agreements for anyone using the intra-State grid. Pages 1-3 are a table of contents; the operative text begins at p4.
Section 1 (p4) lays down general provisions: payment of intra-State transmission and wheeling charges alongside inter-State charges, adherence to the Act, Rules and Commission orders, and 15-minute-block energy accounting and settlement. It also sets out how captive generating plant status is verified against Rule 3 of the Electricity Rules, 2005. Section 2 (p4-6) sets out how to obtain the distribution licensee's consent — the nodals to whom applications go, the consent formats (1A/1B for applicants, 2A/2B from the DISCOM), the 3-working-day / 2-working-day processing clock, the mandatory nature of consent for all consumers and generators irrespective of voltage, and the CGP approval path through Formats 3A/3B/3C with scrutiny by the DISCOM nodal agency. It also mandates online processing within three months of issue and provides registration and relinquishment flow charts (p6-8).
Pages 9-34 are the proforma annexures: application and consent formats for generators and consumers, the CGP energy wheeling application and its document list, the Energy Wheeling Agreement (with 25 clauses on scheduling, losses, DSM, metering, CGP status, disputes and agreement period), the Energy Purchase Agreement (definitions, grid-connectivity conditions, rate, billing, payment security, arbitration, force majeure) and reporting Formats A/B and Annexure-I.
Section 3.0 (p35-41) begins the detailed access-grant procedure: eligibility and non-eligibility (outstanding dues, insolvency), criteria for granting open access including the no-augmentation rule for medium/short-term access, and the full long-term open access route — where to apply, application fees by capacity band and injection/drawal location, documents, bank guarantee requirements, application processing, concurrence timelines, agreement signing, and the deemed-consent provision for distribution licensee consent.
Read with this
The regulation
- Dated 13 Mar 2014Grid Connectivity and Intra-State Open Access Regulations, 2014
Amendments and corrections
- Dated 16 Mar 2022Grid Connectivity and Intra State Open Access Regulations, 2014 — Amendment, 2022
- Dated 18 Sep 2025Changes some provisions: Terms and Conditions for Green Energy Open Access Regulations, 2025
Procedures and orders made under it
Proposed changes (drafts with no final yet)
Earlier drafts
One more document belongs here and is not on Voltaic: a copy in another language.
Voltaic last read TNERC's website for final documents on 29 Sep 2026 and for drafts on 24 Nov 2026. A document TNERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.