Bihar Electricity Supply Code, 2007 — 3rd Amendment, 2013

Bihar Electricity Supply Code (3rd Amendment), 2013

AmendmentDated 28 Feb 2013No. BERC–Regulation 6/06 (Part–IV–I)-02––01 dated 28th February 2013

Amends the Bihar Electricity Supply Code, 2007.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on berc.co.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The Bihar Electricity Regulatory Commission issued this amendment on 28 February 2013, using its powers under s.181(1) and s.181(2)(x) read with s.50 of the Electricity Act, 2003 to remove difficulties for stakeholders under the Bihar Electricity Supply Code, 2007 (p2). It substitutes four clauses in Chapter 7 of that Code; the Hindi text on p1 mirrors the English text on pp2–4.

Clause 7.12(7) is replaced to govern reductions in contract demand: a fresh agreement for the reduced load, recalculation of the security deposit, adjustment of any excess in future bills, no compulsory period for supply at the reduced load, and termination after proper notice (p2–3).

Clause 7.13(2) is replaced to set the compulsory period for availing supply, running from commencement of supply or the initial agreement period and varying by consumer category, and to let the licensee revise agreement formats with Commission approval so that they stay consistent with the Act, Rules, Regulations and this Code (p3).

Clause 7.14(1) is replaced to provide that an agreement remains in force after its initial period until terminated, to set category-based termination notice periods, to make a consumer liable for tariff-order charges if it exits before the initial period ends, and to require a special meter reading and a final bill with termination effective on the last day of the billing month (p3).

Clause 7.15(1) is replaced to let the licensee take an initial security deposit sized on estimated consumption over a category-specific period, with a table distinguishing agricultural, seasonal and other consumers, and to permit instalment payment subject to a minimum upfront share with delayed payment surcharge on the reducing balance (p3–4). Commencement is tied to publication in the Bihar Gazette, whose date is not printed (p2).

Standard name
Electricity Supply Code
Primary topics
Conditions of supply, Security deposit, New connections and load changes

Read with this

Voltaic last read BERC's website for final documents on 24 Nov 2026 and for drafts on 21 Nov 2026. A document BERC issued after the page that lists it was read may not be held by Voltaic yet.