Power Procurement from New and Renewable Sources of Energy Regulations, 2008
The Power Procurement from New and Renewable Sources of Energy Regulations, 2008.
RegulationDated 8 Feb 2008In force from 15 May 2006TNERC/NCES Regn./16/1 dated 8.2.2008
7 amendments to it are on Voltaic, the latest dated 19 Jan 2013.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is TNERC's principal regulation for procuring power from new and renewable sources of energy (NRSE) — mini/micro hydel, wind, solar, biomass, bagasse cogeneration and urban/municipal waste — and it governs the terms on which Tamil Nadu's distribution licensees buy such power (p1–2).
Regulation 1 fixes the title, extends the rules to the whole State and gives them retrospective force: they are deemed to have come into force on 15 May 2006, the date of the Commission's earlier order No. 3, and apply to NRSE and cogeneration plants whose PPAs were signed on or after that date. Older contracts stay in force, but the parties may jointly opt to renegotiate and must execute a revised agreement within thirty days (p1–2).
Regulation 2 defines the working vocabulary, including firm and infirm power and what counts as a new and renewable source. Regulation 3 sets the promotional framework: the minimum percentage of energy each distribution licensee must buy from renewables is whatever the Commission's orders stipulate from time to time, subject to availability, with the licensee disclosing planned NRSE purchases in its ARR filing; bagasse/biomass plants face a cap on conventional fuel; evacuation is built to the Intra State Open Access Regulations 2005, CEA connectivity standards 2007 and the State Grid Code; and banking, payment security and interfacing costs are addressed (p3).
The tariff part (p4–5) lays out the process — suo motu or on application, public comment, hearing, then a general or specific tariff order — the external guidance followed (CERC, National Electricity Policy, Tariff Policy, Rural Electrification Policy, Forum of Regulators, Central and State Governments), case-by-case treatment for small hydro above a stated capacity, adoption of tariffs set through s.63 bidding, and possible technology-linked allowances or cost-plus single-part average tariffs.
Regulations 5–8 cover wheeling-adjustment charges, a twenty-year agreement period with a three-year control period, model EPA/EWA filing plus monthly PPA reporting with fees, and the list of open issues (demand and energy charges, transmission and wheeling charges, reactive power, peak/off-peak adjustment, open access fees and so on) that the Commission may settle for captive use and third-party sale. Regulations 9–10 give the Commission power to remove difficulties and to amend the regulations.
Read with this
Amendments and corrections
- Dated 1 Dec 2008Power Procurement from New and Renewable Sources of Energy (First Amendment) Regulations, 2008
- Dated 24 Dec 2008Power Procurement from New and Renewable Sources of Energy (Second Amendment) Regulations, 2008
- Dated 8 Jun 2009Power Procurement from New and Renewable Sources of Energy (Second Amendment) Regulations, 2009
- Dated 7 Jan 2010Power Procurement from New and Renewable Sources of Energy Regulations, 2008 — Consolidated as amended up to 31.12.2009
- Dated 18 Mar 2011Power Procurement from New and Renewable Sources of Energy Regulations, 2008 — Consolidated to 31-12-2010
- Dated 1 Jul 2011Power Procurement from New and Renewable Sources of Energy (Amendment) Regulations, 2011
- Dated 19 Jan 2013Power Procurement from New and Renewable Sources of Energy Regulations, 2008 — Amendment, 2013
Proposed changes (drafts with no final yet)
Earlier drafts
9 more documents belong here and are not on Voltaic: 8 copies in another language and 1 draft or notice on a draft.
Voltaic last read TNERC's website for final documents on 29 Sep 2026 and for drafts on 24 Nov 2026. A document TNERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of TNERC's website on 29 Sep 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.