Power Procurement from New and Renewable Sources of Energy Regulations, 2008 — Amendment, 2013

Amendment to the Power Procurement from New and Renewable Sources of Energy Regulations, 2008

AmendmentDated 19 Jan 2013TNERC / NCES Regn /16/11 dated 19-01-2013

Amends the Power Procurement from New and Renewable Sources of Energy Regulations, 2008.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on tnerc.tn.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a short TNERC amendment — notification no. TNERC / NCES Regn /16/11, dated 19-01-2013 — making four changes to the Power Procurement from New and Renewable Sources of Energy Regulations, 2008, packaged with an explanatory statement and a side-by-side comparison table (p1, p3–5).

The operative part (p1–2) substitutes regulation 3(3) so the generator, rather than the licensee, provides evacuation facilities from the point of generation to the interconnection point — including metering, protection and the interface line — in line with the Commission's Intra State Open Access Regulations, the CEA Technical Standards for Grid Connectivity and the Tamil Nadu Electricity Grid Code. It deletes the words "and allied issues" from regulation 6; rewrites regulation 7 so that distribution licensees, not the Commission, must file a model Energy Purchase Agreement / Energy Wheeling Agreement — discussed with generators and open access customers — for Commission approval within one month of the Commission issuing a tariff order; and drops the word "incentive/" from item (8) of regulation 8.

The explanatory statement (p3) gives the reasoning: the existing provisos to regulation 3(3) are inconsistent with section 10(1) of the Electricity Act 2003; a tariff revision binds only generators commissioned after the revised order, whereas allied issues bind all NCES generators; licensees are better placed to draft EPA/EWA, though the Commission still approves the model after taking stakeholder views; and the power factor incentive has been withdrawn, consistent with an amendment already made in the Distribution Code.

Pages 4–5 set out the existing and amended provisions side by side for regulations 3, 6, 7 and 8.

Standard name
Power Procurement Regulations, Renewable Energy Tariff Regulations
Primary topics
Power procurement and PPAs, Renewable energy tariff

Read with this

Voltaic last read TNERC's website for final documents on 29 Sep 2026 and for drafts on 24 Nov 2026. A document TNERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on tnerc.tn.gov.in ↗

Report an issue with this document