Hydro Generation Tariff Regulations, 2011 — Second Amendment, 2013

Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) (Second Amendment) Regulations, 2013

AmendmentDated 1 Nov 2013No. HPERC/F(5)(3)(1)(Gen).- dated the 1stNovember, 2013

Replaced by Hydro Generation Tariff Regulations, 2024

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Hydro Generation Tariff Regulations, 2011.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal- (a) anything done or any action taken or purported to have been done or taken under the repealed Regulations shall, in so far as it is not inconsistent with the provisions of these Regulations, be deemed to have been done or taken under the corresponding provisions of these Regulations; (b) the provisions concerning the tariff order made for the control period ending on the 31st March, 2024 and the provisions for conduct of the proceedings (including review petitions) for its revocations, variation or alternation as, stood before such repeal, shall continue to be in force.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on hperc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the second amendment to HPERC's 2011 Hydro Generation Tariff Regulations, notified at Shimla on 1 November 2013 under s.181(2)(zd)–(zf) read with ss.61, 62 and 86 of the Electricity Act (p1). It comes into force on publication in the Rajpatra, but applies to tariff orders for control periods commencing on or after 1 April 2014 (p1). The Commission states it is preparing to determine hydro tariffs for the next control period, so the amendment reworks the machinery of multi-year tariff setting rather than any single rate.

The definitions clause recasts regulation 3: ARR, mid-term performance review (MPR) and a redefined availability factor (NAPAF) are inserted or substituted, 'annual performance review' is replaced throughout by 'mid-term performance review', and date references are rewritten to the first year of the control period (p1–2). Regulation 9 (True Up) is replaced wholesale, setting when true-ups happen, the principles applied (capital investment, depreciation, financing cost) and how surpluses, deficits, controllable factors, force majeure, change in law and taxes are treated (p2–3).

Several financial parameters are reset: the SBI benchmark for working-capital interest and for loan interest becomes Base Rate plus 350 basis points (p3), return on equity is grossed up at the latest audited tax rate with annual true-up (p3–4), and regulation 22 is replaced with a full O&M expense regime covering base years, new stations, escalation formulae and provisions (p4–6). Cost-overrun treatment for renovation and modernisation is added (p3), a per-unit rate in regulation 26(7) is raised (p6), and compliance with CEA regulations on safety is mandated (p6). Filing obligations are rewritten — multi-year ARR and tariff filings at least 120 days ahead of the control period, electronic filing, public disclosure, and the MPR petition process (p6–8) — and regulation 43 bars income-tax recovery from beneficiaries in view of pre-tax return on equity (p8).

Standard name
Generation Tariff Regulations
Primary topics
Generation tariff, Multi Year Tariff (MYT), Tariff determination

Read with this

The regulation

Commencement notices and reasons

Procedures and orders made under it

Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on hperc.org ↗

Report an issue with this document