Hydro Generation Tariff (First Amendment) Regulations, 2011

Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) (First Amendment) Regulations, 2011

AmendmentDated 30 Jul 2011HPERC/Gen/479 dated 30th July, 2011

Replaced by Hydro Generation Tariff Regulations, 2024

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Hydro Generation Tariff Regulations, 2011.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal- (a) anything done or any action taken or purported to have been done or taken under the repealed Regulations shall, in so far as it is not inconsistent with the provisions of these Regulations, be deemed to have been done or taken under the corresponding provisions of these Regulations; (b) the provisions concerning the tariff order made for the control period ending on the 31st March, 2024 and the provisions for conduct of the proceedings (including review petitions) for its revocations, variation or alternation as, stood before such repeal, shall continue to be in force.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on hperc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a two-page amendment by the Himachal Pradesh Electricity Regulatory Commission to its own 2011 hydro generation tariff regulations, issued at Shimla on 30 July 2011 as notification No. HPERC/Gen/479 (p1).

The preamble explains why the change is needed (p1–2). The principal Regulations require the capital cost of a hydro project to be determined on actual expenditure, with the capital cost admitted by the Commission after prudence check forming the tariff base (p1). Those Regulations laid down no benchmark norms for that prudence check, and the Commission says framing its own norms could take considerable time (p1). The Central Electricity Authority has, however, issued guidelines for formulating and examining DPRs for hydro electric schemes containing certain benchmarks (p1).

The operative part is a single amendment to regulation 11(2) (p2). It inserts a new first proviso allowing prudence check of capital cost against benchmark norms the Commission may lay down from time to time, and substitutes the existing first proviso so that where no such norms have been laid down, prudence check may instead follow the CEA's benchmark norms and guidelines (p2). Regulation 1 gives the short title and makes commencement turn on publication in the Rajpatra, Himachal Pradesh; that Gazette date is not printed here (p2).

Standard name
Generation Tariff Regulations
Primary topics
Generation tariff, Capital cost and investment

Read with this

The regulation

Commencement notices and reasons

Procedures and orders made under it

Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.