Truing up of APPC for FY 2017-18 and provisional APPC for FY 2018-19, 2018

Truing up of Average Pooled Power Purchase Cost [APPC] for the Financial Year 2017-18 and notifying provisional APPC for the Year 2018-19

OrderDated 2 Apr 2018Published in the Gazette 4 Apr 2018No. Y/01/18 dated 02.04.2018

Made under the Procurement of Energy from Renewable Sources Regulations, 2011.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on kerc.karnataka.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a one-page KERC order, published in the Karnataka Gazette of 4 April 2018 and issued on 2 April 2018, that closes out the Average Pooled Power Purchase Cost (APPC) for FY 2017-18 and fixes a provisional APPC for FY 2018-19 for Renewable Energy Certificate purposes (p1).

The preamble recalls that the Commission's notification of 30 March 2017 had set a provisional APPC of Rs 3.57/unit for FY 2017-18, subject to truing up on actuals; with the ESCOMs' FY 2016-17 accounts now finalised, the FY 2017-18 APPC works out to Rs 3.64/unit. Because the ESCOMs will take time to finalise FY 2017-18 power purchase quantum and cost, the Commission adopts the same Rs 3.64/unit as an interim figure for FY 2018-19 (p1).

The operative order notifies that rate for FY 2018-19 with effect from 1 April 2018 until further orders and subject to truing up as per actuals. It then directs that the 7 paise/unit variation for FY 2017-18 - the gap between the provisional and actual APPC - be paid by ESCOMs to the affected RE generators in three equal monthly instalments, limited to the energy supplied under APPC between 1 April 2017 and 31 March 2018 (p1).

Standard name
RPO Regulations
Primary topics
Renewable energy certificates (REC)

Read with this

5 more documents belong here and are not on Voltaic: 5 copies in another language.

Voltaic last read KERC's website for final documents on 24 Nov 2026 (3 pages) and for drafts on 23 Nov 2026. A document KERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on kerc.karnataka.gov.in ↗

Report an issue with this document