Short Term Open Access Regulations, 2010 — First Amendment, 2018 — Order

In the matter of formulation of the Himachal Pradesh Electricity Regulatory Commission (Short Term Open Access) (First Amendment) Regulations, 2018.

OrderDated 11 Jun 2018Published in the Gazette 20 Mar 2018

Made under the Short Term Open Access Regulations, 2010.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on hperc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is HPERC's order disposing of objections to, and approving, the First Amendment to its 2010 Short Term Open Access Regulations. It is not the amendment text itself: the order records why the Commission pressed ahead and directs notification. Pages 1–2 set out the background: HPSEBL's petition for FY 2017-18 additional surcharge, its request that STOA consumers schedule at least 24 hours to stop frequent switching, and the FoR working-group/62nd-meeting endorsement. They also record the draft amendment notified on 14 March 2018 and published in the Rajpatra on 20 March 2018, newspaper notices on 24 March 2018, and stakeholder letters.

Pages 3–4 summarise the public hearing of 19 May 2018: IEX, STOA consumers such as Ambuja, ACC and Inox objected; HPSEBL, SLDC and HPPTCL supported the proposal, with HPSEBL wanting 24 hours and SLDC wanting 8 continuous hours.

Pages 4–13 are the Commission's issue-by-issue analysis. It rejects arguments that the draft is ultra vires s.42(2) or anti-competitive, finds the DISCOM's switching/gaming concern genuine, and relies on the distinction between normal demand diversity and STOA uncertainty. It retains the 8 continuous-hour uniform day-ahead schedule, not the 24 hours proposed by MoP/FoR and HPSEBL, while noting that a consumer may still avail STOA for less than 8 hours if the final schedule so provides, with possible higher additional surcharge. It treats the higher additional surcharge as only an enabling provision; the rate and methodology are left for a later determination. It clarifies that the amendment concerns day-ahead schedules submitted by consumers, not schedules approved by the authority. The only accepted textual change is replacing 'competent authority' with 'agency competent to finalize and approve the day ahead schedule' (p12). Paragraph 12 records the decision to retain the draft without other changes and approve it for notification (p12–13), signed at Shimla on 11 June 2018. Annexure A (p14) lists public-hearing participants.

Standard name
Open Access Regulations
Primary topics
Open access, Open access charges, Scheduling and despatch

Read with this

Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.