HPERC · Himachal Pradesh Electricity Regulatory Commission
Determination of Open Access Charges Order, 2009
Himachal Pradesh Electricity Regulatory Commission (Determination of Open Access Charges) Order, 2009
OrderDated 25 Nov 2009No. HPERC/418.- dated 25th November, 2009
Made under the Short Term Open Access Regulations, 2010.
Summary
Summary written by software. Check the regulator's original before you rely on it.
A two-page order of the Himachal Pradesh Electricity Regulatory Commission, dated 25 November 2009, fixing what an open access customer must pay to use the State's transmission and distribution networks (p1). It is made under the Commission's Open Access Regulations 2005 (regs 15 and 33), the Transmission Tariff Determination Regulations 2007 (reg 32) and the Cross Subsidy Surcharge Regulations 2006 (reg 3), and comes into force on publication in the Rajpatra, Himachal Pradesh — no Gazette date is printed (p1).
Clause 1 gives the short title and commencement. Clause 2 is the sunset clause: the order runs only to 31 March 2011 unless the Commission orders its continuation, with or without variations (p1).
Clause 3 is the operative part, split by where the customer sits. For open access customers in transmission it sets a transmission charge of Rs. 43358.92/MW/month and an SLDC/operating charge of Rs. 1,000/- per day or part of a day for each transaction (p1). For open access customers in distribution it sets wheeling charges of 71 paise/unit — expressly adopting the rate already determined in the FY 2009-2010 tariff order for the Himachal Pradesh State Electricity Board — the same per-transaction SLDC charge, and category-wise cross-subsidy surcharges that are positive for the LS EHT category and Nil for the LS HT and BS HT categories (p1–2).
The order is signed by the Secretary by order of the Commission (p2).
Read with this
The regulation
- Dated 2 May 2010Short Term Open Access Regulations, 2010
Amendments and corrections
- Dated 11 Jun 2018Short Term Open Access Regulations, 2010 — First Amendment, 2018
- Dated 30 Aug 2024Short Term Open Access Regulations, 2010 — Second Amendment, 2024
Commencement notices and reasons
Procedures and orders made under it
- Dated 1 Dec 2011Determination of Open Access Charges Order, 2011
- Dated 26 Jun 2012Determination of Transmission and Tentative Wheeling Charges under Open Access Charges Order, 2012
- Dated 29 May 2013Determination of Transmission, Wheeling, SLDC and Cross Subsidy Surcharge under Open Access Charges Order, 2013
- Dated 11 Jun 2018Short Term Open Access Regulations, 2010 — First Amendment, 2018 — Order
- Dated 29 Mar 2022Captive Generating Plant Status Verification Procedure, Himachal Pradesh, 2022
- Dated 29 Mar 2022Captive Generating Plant Status Verification Procedure, Himachal Pradesh
Earlier drafts
One more document belongs here and is not on Voltaic: a corrigendum.
Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.