APERC · Andhra Pradesh Electricity Regulatory Commission

Practice Directions for Release of LT Agricultural Connections by DISCOMs, 2021

APERC - Practice directions for release of LT agricultural connections by DISCOMs - Issued - Regarding.

OrderDated 23 Mar 2021Practice Directions No. 02/APERC/ TR-1007 /2021 dated 23-03-2021

Made under the Licensee's Duty for Supply of Electricity on Request Regulation, 2013.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on aperc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a three-page set of practice directions issued by the Andhra Pradesh Electricity Regulatory Commission to the three Andhra Pradesh distribution licensees, telling them how to run the queue for new low-tension agricultural connections (p1–3).

The Commission opens by recording that its own licensing and standards-of-performance regulations — the duty to supply on request and the standards of performance — are being breached in practice. It lists the failures it observed: waiting lists kept at Section level are poorly maintained, acknowledgements are not issued in time, charges are not intimated in writing, waiting-list serial numbers are never communicated in writing, later applicants are released ahead of earlier ones, and distribution transformers are released and charged at local officers' discretion. It says these findings come from data drawn from one selected Section in each DISCOM and that the violations were communicated to the DISCOMs (p1–2).

The operative part first restates the regulation's own requirements and directs the DISCOMs to comply without fail. It then adds a uniform statewide procedure for releasing agricultural connections: acknowledgement, written intimation of charges, a Section-level seniority list built on the date and time of payment of estimated charges, weekly upload of additions and releases on the DISCOM website, combined Sub-Division/Division-level waiting lists published and updated weekly, and release strictly in combined-list order subject to Government out-of-turn releases for SC and ST applicants (p2–3).

The directions also allocate responsibility for distribution transformers down the chain, from Corporate Office to Circles to Divisions to Sections, in proportion to pending applications, and say that any Government annual quota for agricultural releases will be allocated through the same procedure (p3). The Commission warns that non-adherence will attract action under the Electricity Act, 2003 (p3).

Standard name
Duty to Supply on Request, Standards of Performance
Primary topics
Agricultural supply, New connections and load changes

Read with this

Consolidated copies, for reference (1)

Voltaic last read APERC's website for final documents on 24 Nov 2026 (2 pages) and for drafts on 21 Nov 2026. A document APERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on aperc.gov.in ↗

Report an issue with this document