Collection of Development Charges for Multi-storied Buildings, Commercial Complexes and Apartments — Guidelines, 2015

Collection of Development charges in case of multistoried buildings/Commercial complexes/Apartments and individual houses- Guidelines issued.

OrderDated 29 May 2015Proceeding No. Secy/10/2015 dated 29-05-2015

Made under the Licensee's Duty for Supply of Electricity on Request Regulation, 2013.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on aperc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a two-page APERC proceeding (No. Secy/10/2015, dated 29 May 2015) issuing guidelines to distribution licensees on when they may recover the full cost of a dedicated distribution transformer from a consumer, as opposed to levying only normative development charges. It follows a suo-motu examination of development-charge levy for multi-storied buildings, commercial complexes, apartments and individual houses (p1).

Page 1 recites the enabling text — clause 8 of the APERC (Licensee's duty for supply of electricity on request) Regulation, 2013 (Regulation 4 of 2013). That clause authorises development charges on a normative, shallow-approach basis limited to the next higher voltage level, permits recovery of full transformer cost where a dedicated transformer is provided to commercial complexes, apartments and multi-storied buildings, and addresses temporary supply, change of category and splitting of service (p1–2).

The Commission then exercises clause 8(1) to clarify clause 8(3): the right to collect full transformer cost is confined to multi-storied buildings, commercial complexes and apartments with a dedicated transformer where the building height is 15 metres or more above the stilt floor (p2). Licensees must withdraw any earlier orders, circulars or memos on the subject that conflict with these guidelines within 15 days and report compliance, and must implement clause 8(4) of the Regulation in true spirit (p2). The order is signed by the Commission on 29 May 2015 (p2).

Standard name
Duty to Supply on Request
Primary topics
Connection and miscellaneous charges, Supply to buildings and colonies, New connections and load changes

Read with this

Procedures and orders made under it

Consolidated copies, for reference (1)

Voltaic last read APERC's website for final documents on 24 Nov 2026 (2 pages) and for drafts on 21 Nov 2026. A document APERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on aperc.gov.in ↗

Report an issue with this document