Procurement of Energy from Renewable Sources (Third Amendment) Regulations, 2022 — Draft

Gujarat Electricity Regulatory Commission (Procurement of Energy from Renewable Sources) (Third Amendment) Regulations, 2022

Draft amendmentDated 30 Jan 2022

Draft

A proposal that has since been finalised as the Procurement of Energy from Renewable Sources (Third Amendment) Regulations, 2022.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on gercin.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a draft amendment by the Gujarat Electricity Regulatory Commission to its 2010 renewable-procurement regulations, put out for previous publication (consultation), with the notification number left blank and no issue date printed (p1). It is short — four operative clauses plus a signature block — and does three things.

First, it rewrites the definition of "renewable energy sources" in Regulation 2(p), retaining the list of eligible non-conventional technologies (small/mini/micro hydro up to and including 25 MW, wind, solar, biomass, bagasse, bio-fuel cogeneration, municipal waste) and adding that large hydro projects above 25 MW commissioned after 8 March 2019 count only towards the Hydro Power Purchase Obligation, with a narrow route for LHP energy to serve solar and other non-solar RPO once compliance reaches 85% (p1–2).

Second, it replaces Table II of Regulation 4.1 — the table earlier substituted by the 2018 Second Amendment — setting out the year-wise minimum RPO percentages for wind, solar, HPO, others and total from FY 2017-18 to FY 2023-24 (p2).

Third, it substitutes para 2 of Regulation 4.1 with a set of provisos (p2–3): how HPO is to be met from eligible large hydro (including pumped storage) commissioned between 08.03.2019 and 31.03.2024, limited to 70% of generated capacity for 12 years and excluding free power and Local Area Development Fund contributions; the availability of a Hydro Energy Certificate mechanism to distribution licensees; use of State-consumed free power towards HPO; and carry-over of a shortfall in one renewable category into the others. A final proviso continues the FY 2023-24 targets into FY 2024-25 and beyond unless the Commission specifies otherwise.

The regulations extend to the whole of Gujarat and take effect from Gazette publication, the date of which is not printed (p1).

Standard name
RPO Regulations
Primary topics
Renewable purchase obligation (RPO / RCO)

Read with this

Procedures and orders made under it

Proposed changes (drafts with no final yet)

Voltaic last read GERC's website for final documents on 24 Nov 2026 (7 pages) and for drafts on 23 Nov 2026. A document GERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on gercin.org ↗

Report an issue with this document