Procurement of Energy from Renewable Sources Regulations, 2010 — First Amendment, 2014

Gujarat Electricity Regulatory Commission (Procurement of Energy from Renewable Sources) (First Amendment) Regulations, 2014

AmendmentDated 4 Mar 2014No. 2 of 2014 dated 04 /03 /2014

Replaced by Procurement of Energy from Renewable Sources Regulations, 2025

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Procurement of Energy from Renewable Sources Regulations, 2010.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on gercin.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The Gujarat Electricity Regulatory Commission's First Amendment to its 2010 renewable procurement regulations (Notification No. 2 of 2014, signed 4 March 2014) makes three targeted changes to the parent framework (p1, p3).

Section 3 inserts a definition of Average Power Purchase Cost into Regulation 2.1 of the Principal Regulations: the weighted average pooled price at which a distribution licensee bought electricity in the previous year, including the cost of self-generation but excluding supply from renewable sources (p2).

Section 5 adds Regulations 5.4 and 5.5. These require the Commission to determine that cost annually for each distribution licensee, and oblige the licensee to pay it — for the electrical component of renewable projects registered under CERC's REC scheme, and to REC-scheme RE generators selling to captive users or third parties in respect of energy surplus to that consumption (p3). The payment obligation attaching to these two clauses is backdated to 1 April 2014 (p1).

Section 4 substitutes Table 1 of Regulation 4.1, restating year-wise renewable purchase obligation percentages split between wind, solar and other technologies, with the trajectory running through 2016-17 (p2). The substituted table re-states obligations for years preceding the amendment itself.

Section 1 gives the short title and Gujarat-wide extent, and defers commencement to Gazette publication except for the two new cost-pass-through clauses (p1). The Gazette date is not printed in this text.

Standard name
RPO Regulations
Primary topics
Renewable purchase obligation (RPO / RCO), Renewable energy certificates (REC)

Read with this

Procedures and orders made under it

Proposed changes (drafts with no final yet)

Voltaic last read GERC's website for final documents on 24 Nov 2026 (7 pages) and for drafts on 23 Nov 2026. A document GERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on gercin.org ↗

Report an issue with this document