GERC · Gujarat Electricity Regulatory Commission

Procurement of Energy from Renewable Sources Regulations, 2010 — Statement of Reasons

Procurement of Energy from Renewable Sources Regulations, 2010

Statement of reasonsDated 17 Apr 2010

Replaced by Procurement of Energy from Renewable Sources Regulations, 2025

See that regulation for the date it took effect and for anything it keeps in force.

The commission's reasons for the Procurement of Energy from Renewable Sources Regulations, 2010 or one of its amendments.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on gercin.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The document is the Gujarat Electricity Regulatory Commission's Statement of Reasons for its proposed Procurement of Energy from Renewable Sources Regulations, 2010 (p1, p21). It is not the regulation itself; it records the Commission's background, the objections received, its analysis, and its decisions to be incorporated before publication in the Official Gazette (p21).

Pages 1–4 set out the statutory and policy background: the Electricity Act's renewable promotion mandate, the National Action Plan on Climate Change, the National Electricity Policy and Tariff Policy, the earlier 2005 Regulation No. 15, the 2009 draft, the public notice, and the litigation history that made that draft non-existent (p1–4). Pages 4–5 describe the fresh 2010 draft, 24 stakeholder responses and the 4 March 2010 public hearing.

Pages 5–11 deal with preliminary objections. The Commission rejects a challenge to its jurisdiction, finding power under section 86(1)(e) read with sections 61(h) and 181 of the Electricity Act (p5–9). It also retains Renewable Energy Certificate provisions on the basis of CERC's REC framework and the Forum of Regulators model (p9–11). Pages 11–15 justify applying RPO to open access consumers and captive users, while limiting it for the present to captive plants of 5 MW or more (p14–15). Pages 15–16 hold that only cogeneration from renewable sources counts toward RPO. Pages 16–18 revise the RPO trajectory by source category after a GEDA assessment and decide not to fix a longer-term trajectory. Pages 18–19 align definitions with CERC REC regulations. Pages 19–21 cover default consequences and the default fund, grid connectivity, cross-subsidy and third-party sale, and the State Agency, before directing Gazette publication of the 08/01/2010 draft with changes (p21).

Standard name
RPO Regulations
Primary topics
Renewable purchase obligation (RPO / RCO), Renewable energy certificates (REC), Open access

Read with this

Procedures and orders made under it

Proposed changes (drafts with no final yet)

Voltaic last read GERC's website for final documents on 24 Nov 2026 (7 pages) and for drafts on 23 Nov 2026. A document GERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on gercin.org ↗

Report an issue with this document