MERC · Maharashtra Electricity Regulatory Commission

Explanatory Memorandum on Draft Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation (First Amendment) Regulations, 2023

EXPLANTORY MEMORANDUM (EM) ON DRAFT MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (FORECASTING, SCHEDULING AND DEVIATION SETTLEMENT FOR SOLAR AND WIND GENERATION) (FIRST AMENDMENT) REGULATIONS, 2023

Explanatory memorandum to a draftReleased with the draft dated 21 Dec 2023

Explanatory memorandum to the Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation Regulations, 2018 — First Amendment, 2023 — Draft.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on merc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Commission's explanatory memorandum for the draft First Amendment to its 2018 Forecasting, Scheduling and Deviation Settlement Regulations for solar and wind generation, issued in December 2023 (p1, p8, p14). It is the rationale document that sits alongside the draft amendment; it does not reproduce the amended clauses (p14, p32, p75). Its audience is the Commission's stakeholders—wind and solar generators, QCAs, distribution licensees, MSLDC, MSPC and consumer representatives—and it is structured as a consultation paper that may also guide the procedures MSLDC will prepare (p14, p39, p70).

Chapter 1 (pp8–15) recounts why the 2018 regulations were made, how commercial implementation began on 6 January 2020, and the developments that prompted review: the state DSM regulations, working-group reports, Commission orders, CERC's 2022 DSM regulations and 6 February 2023 order, the national non-fossil capacity target, and MSKVY 2.0 (pp8–13). Chapter 2 (pp16–36) reviews the absolute-error formula and the error-band/deviation-charge framework. It rejects a shift away from available capacity as the denominator, proposes tighter bands and revised charge slabs, and explains the separate treatment of intra-state and inter-state transactions, including proposed deletion of Regulation 7.6 and changes to the Annexure (pp16–36).

Chapter 3 (pp37–75) is the core policy proposal: shifting wind and solar generators from actual-generation payment to scheduled-generation payment, broadly along CERC lines (pp37–57). It compares MERC and CERC frameworks, summarises stakeholder concerns, and then works through implementation—metering and communication, a QCA portal, PPA-rate declaration and contract mapping, schedule certification, RPO treatment, PPA amendments, trial-mode operation, roles and dispute resolution through MSPC (pp58–71). It sets out a phased transition from detailed procedure to hardware, software, trial run and rollout, with a trial period of at least twelve months (pp71–74).

Chapter 4 (pp76–81) covers residual changes: aligning schedule-revision practice with the State Grid Code, limiting frequent minor revisions, removing the MSKVY exemption, strengthening gaming provisions, aligning definitions and relaxing the separate-feeder condition for inter-state transactions. The Annexure (pp82–106) supplies the scheduling-accuracy analysis by technology, season and QCA, plus sample financial comparisons of the MERC and CERC regimes that underpin the proposals.

Standard name
Forecasting, Scheduling and DSM for Wind and Solar
Primary topics
Scheduling and despatch, Deviation settlement (DSM), Metering

Read with this

3 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text and 1 draft or notice on a draft.

Voltaic last read MERC's website for final documents on 24 Nov 2026 (8 pages) and for drafts on 24 Nov 2026. A document MERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on merc.gov.in ↗