Skip to content

MERC · Maharashtra Electricity Regulatory Commission

Removal of Difficulty in implementation of Procedure under Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation Regulations, 2018

Removal of Difficulty in implementation of Procedure under MERC (Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation) Regulations, 2018

OrderDated 18 Mar 2019

Made under the Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation Regulations, 2018.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on merc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a short MERC order of 18 March 2019 (p1) resolving an implementation difficulty in the fee schedule of the Detailed Procedure approved under the MERC (Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation) Regulations, 2018. It records that MSLDC submitted the Detailed Procedure under Regulation 5.20, which the Commission approved on 7 December 2018, and that Clause 7.1 of that Procedure sets out the MSLDC fee and charges payable by the QCA — registration, scheduling, revision-in-schedule, forecasting services, corpus and top-up, and other charges (p1).

The trigger was a stakeholders' co-ordination meeting on 26 February 2019, reported to the Commission by MSLDC's letter of 12 March 2019, at which stakeholders objected to the level of QCA registration, scheduling and intraday schedule-revision charges, given the number of permissible revisions needed for infirm solar and wind generation, and compared them unfavourably with charges in other states; they asked for scheduling and revision charges to be waived (p2).

The Commission accepts that renewable generation is infirm and that close-to-despatch schedule revision is how forecast accuracy and grid stability are achieved (p2). Exercising powers under Regulation 19 of the Regulations and Clause 16 of the Detailed Procedure, it waives the charges for scheduling and for revision of scheduling until further Order, and substitutes a revised Abstract of Payments for the table at page 48 of the Procedure (p2). The revised table keeps registration charges, forecasting service charges, corpus, top-up of corpus and any other charges unchanged, and shows NIL against scheduling charges and revision in schedules (p2–3). The order is signed by two Members and the Chairperson (p3).

Standard name
Forecasting, Scheduling and DSM for Wind and Solar
Primary topics
Scheduling and despatch, SLDC and RLDC fees and charges

Read with this

3 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text and 1 draft or notice on a draft.

Voltaic last read MERC's website for final documents on 24 Nov 2026 (8 pages) and for drafts on 24 Nov 2026. A document MERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on merc.gov.in ↗

Report an issue with this document