MERC · Maharashtra Electricity Regulatory Commission
Removal of Difficulty in implementation of Procedure under Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation Regulations, 2018
Removal of Difficulty in implementation of Procedure under MERC (Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation) Regulations, 2018
OrderDated 18 Mar 2019
Made under the Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation Regulations, 2018.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is a short MERC order of 18 March 2019 (p1) resolving an implementation difficulty in the fee schedule of the Detailed Procedure approved under the MERC (Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation) Regulations, 2018. It records that MSLDC submitted the Detailed Procedure under Regulation 5.20, which the Commission approved on 7 December 2018, and that Clause 7.1 of that Procedure sets out the MSLDC fee and charges payable by the QCA — registration, scheduling, revision-in-schedule, forecasting services, corpus and top-up, and other charges (p1).
The trigger was a stakeholders' co-ordination meeting on 26 February 2019, reported to the Commission by MSLDC's letter of 12 March 2019, at which stakeholders objected to the level of QCA registration, scheduling and intraday schedule-revision charges, given the number of permissible revisions needed for infirm solar and wind generation, and compared them unfavourably with charges in other states; they asked for scheduling and revision charges to be waived (p2).
The Commission accepts that renewable generation is infirm and that close-to-despatch schedule revision is how forecast accuracy and grid stability are achieved (p2). Exercising powers under Regulation 19 of the Regulations and Clause 16 of the Detailed Procedure, it waives the charges for scheduling and for revision of scheduling until further Order, and substitutes a revised Abstract of Payments for the table at page 48 of the Procedure (p2). The revised table keeps registration charges, forecasting service charges, corpus, top-up of corpus and any other charges unchanged, and shows NIL against scheduling charges and revision in schedules (p2–3). The order is signed by two Members and the Chairperson (p3).
Read with this
The regulation
Amendments and corrections
Commencement notices and reasons
- Dated 20 Jul 2018Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation Regulations, 2018 — Statement of Reasons
- Dated 18 Mar 2019Notification of Effective Date for Commercial Arrangement under Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation Regulations, 2018
- Dated 3 Jul 2024Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation (First Amendment) Regulations, 2024 — Statement of Reasons
Procedures and orders made under it
- Dated 7 Dec 2018Forecasting, Scheduling and Deviation Settlement of Solar and Wind Generation Procedure, 2018
- Dated 19 Dec 2019Amended F&S Procedure for Solar and Wind Generation
- Dated 19 Apr 2021Removal of Difficulty in Applicability of State Periphery Charges under the Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation Regulations, 2018 — Order, 2021
Earlier drafts
- Released with the notice dated 27 Feb 2018Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation Regulations, 2018 — Draft
- Dated 27 Feb 2018Public notice: Draft Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation Regulations, 2018 — Public Notice Inviting Comments
- Released with the notice dated 27 Feb 2018File: Draft Solar and Wind Forecasting, Scheduling and Deviation Settlement Framework for Maharashtra, 2018 — Approach Paper
- Dated 21 Dec 2023Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation Regulations, 2018 — First Amendment, 2023 — Draft
- Released with the draft dated 21 Dec 2023Explanatory memorandum: Explanatory Memorandum on Draft Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation (First Amendment) Regulations, 2023
- Dated 22 Dec 2023Public notice: Public Notice on Draft Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation (First Amendment) Regulations, 2023
3 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text and 1 draft or notice on a draft.
Voltaic last read MERC's website for final documents on 24 Nov 2026 (8 pages) and for drafts on 24 Nov 2026. A document MERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.