Recovery of Expenditure for Supply of Electricity (Sixth Amendment) Regulations, 2024 — Finalisation Order

In the matter of draft amendments of the Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity) (Sixth Amendment) Regulations, 2024.

OrderDated 3 Aug 2024Published in the Gazette 25 May 2024

Read with the Recovery of Expenditure for Supply of Electricity Regulations, 2012.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on hperc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

A two-page HPERC order of 3 August 2024 that closes out the consultation on the draft HPERC (Recovery of Expenditure for Supply of Electricity) (Sixth Amendment) Regulations, 2024 and directs that the amendments be notified (p1–2). It is the finalisation record, not the amendment text: no change was made to the draft as published, and the operative wording sits in the notified regulations.

Paragraphs 1–3 set the background. The parent 2012 Regulations were gazetted on 23 May 2012 and have been amended from time to time. HPSEBL has prepared annual cost data books since 2006-07 and has gained sufficient experience; the Commission concluded that the period allowed for capturing the cost of material in those books needed rationalising, along with other need-based changes. The draft amendment was issued on 22 May 2024 and published in the Rajpatra on 25 May 2024 (p1).

Paragraph 4 records the pre-publication process: a public notice in Hindustan Times and Amar Ujala on 8 June 2024 under Rule 3 of the Electricity (Procedure of Previous Publication) Rules, 2005, the full draft on the Commission's website, and a last date of 6 July 2024 for objections and suggestions (p1). Paragraph 5 records letters of 11 June 2024 inviting Industries Associations, the State Government, the Directorate of Energy and the Distribution Licensee to respond (p1–2).

Paragraph 6 states that no comments were received within the stipulated period, repeats the rationale, approves the rationalisation, finalises the draft amendments without change and orders notification (p2). The order is signed by the Chairman and both Members and announced the same day (p2).

Standard name
Recovery of Expenditure and Miscellaneous Charges
Primary topics
Connection and miscellaneous charges

Read with this

Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on hperc.org ↗

Report an issue with this document