Recovery of Expenditure for Supply of Electricity (First Amendment) Regulations, 2015
Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity) (First Amendment) Regulations, 2015
AmendmentDated 22 Jul 2015No. HPERC/419. dated 22nd July, 2015
Amends the Recovery of Expenditure for Supply of Electricity Regulations, 2012.
Summary
Summary written by software. Check the regulator's original before you rely on it.
The two pages bundle two things: a one-page amending notification and the order recording why it was made.
Page 1 is the amendment itself, issued as No. HPERC/419 from Shimla on 22 July 2015 under section 46 read with section 181 of the Electricity Act, 2003. It makes two changes to regulation 5(2) of the HPERC (Recovery of Expenditure for Supply of Electricity) Regulations, 2012: a new first proviso is inserted, and the existing first proviso is re-designated as the "Provided further". The inserted proviso carves out Central and State Government bodies and government agencies. Where such an applicant is willing to deposit the entire estimated or actual cost of the works, including the service line, in advance before the works commence, and that cost is more than the normative Infra Development Charges and the cost of the service line, the applicant need not separately pay IDC under these regulations or the advance cost share for obtaining a Power Availability Certificate under the Himachal Pradesh Electricity Supply Code, 2009. Clause 1 gives the short title and provides that the regulations come into force on publication in the Rajpatra, Himachal Pradesh.
Page 2 is the order, signed by Chairman Subhash C. Negi on 22 July 2015. It records that field officers of the distribution licensee reported that government departments, corporations, PSUs and CPSUs were finding frequent approvals for depositing connection amounts difficult; that the draft amendment was published in the Rajpatra on 12 May 2015 and advertised in two newspapers on 14 May 2015 with 26 days for objections; that no comments were received; and that the draft was therefore finalised as it stood.
Read with this
The regulation
- Dated 18 May 2012Recovery of Expenditure for Supply of Electricity Regulations, 2012
Amendments and corrections
- Dated 21 Sep 2015Recovery of Expenditure for Supply of Electricity (Second Amendment) Regulations, 2015
- Dated 19 Oct 2015Recovery of Expenditure for Supply of Electricity (Third Amendment) Regulations, 2015
- Dated 23 Jan 2017Recovery of Expenditure for Supply of Electricity Regulations, 2012 — Fourth Amendment, 2017
- Dated 5 Sep 2018Recovery of Expenditure for Supply of Electricity (Fifth Amendment) Regulations, 2018
- Dated 5 Aug 2024Recovery of Expenditure for Supply of Electricity Regulations, 2012 — Sixth Amendment, 2024
Commencement notices and reasons
- Dated 18 May 2012Himachal Pradesh Recovery of Expenditure for Supply of Electricity Regulations, 2012 — Statement of Reasons
- Dated 9 Dec 2016Recovery of Expenditure for Supply of Electricity (Fourth Amendment) Regulations, 2017 — Order on draft amendments
- Dated 5 Sep 2018Recovery of Expenditure for Supply of Electricity (Fifth Amendment) Regulations, 2018 — Order
- Dated 3 Aug 2024Recovery of Expenditure for Supply of Electricity (Sixth Amendment) Regulations, 2024 — Finalisation Order
Procedures and orders made under it
- Dated 29 May 2012Fixation of Normative Infrastructure Development Charges, 2012 — Notification
- Dated 7 Jan 2013Normative Infrastructure Development Charges — Provisional Arrangements Extension, 2013
- Dated 5 Jun 2024Approval of Schedule of Service Connection Charges (IDC) under the Recovery of Expenditure Regulations, 2012, 2024
Earlier drafts
- Dated 9 Dec 2016Recovery of Expenditure for Supply of Electricity (Fourth Amendment) Regulations, 2016 — Draft
- Dated 20 Jul 2018Recovery of Expenditure for Supply of Electricity Regulations, 2012 — Fifth Amendment, 2018 — Draft
- Dated 22 May 2024Recovery of Expenditure for Supply of Electricity (Sixth Amendment) Regulations, 2024 — Draft
Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.