CERC · Central Electricity Regulatory Commission

RLDC Fees and Charges Regulations, 2019 — Statement of Reasons

Statement of Reasons (SoR)

Statement of reasonsDated 5 Apr 2019No.- L-1/153/2019/CERC

Replaced by Fees and Charges of Regional Load Despatch Centre and other related matters Regulations, 2024

See that regulation for the date it took effect and for anything it keeps in force.

The commission's reasons for the Fees and Charges of Regional Load Despatch Centre and other related matters Regulations, 2019.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Statement of Reasons (SoR) issued by the Central Electricity Regulatory Commission with the final CERC (Fees and Charges of Regional Load Despatch Centre and other related matters) Regulations, 2019 (p1). It is not the operative regulation: it records why the Commission accepted, rejected or deferred stakeholder comments on the draft notified on 26.2.2019 and describes what changed between draft and final text.

Paragraphs 1.1–1.4 give the background. The draft was issued with an Explanatory Memorandum and drew comments from POSOCO, GRIDCO, GUVNL and PCKL, with POSOCO also making oral submissions at a public hearing on 20.3.2019 (p1–2). The Commission states that the review drew on the CABIL report, "Capacity Building of Indian Load Despatch Centres", produced by a sub-group of the Forum of Regulators' Standing Technical Committee and accepted at the FOR's 65th meeting on 13.11.2018, as well as model LDC fees-and-charges regulations (p1–2).

The bulk of the document (paragraphs 2–20, pp2–14) goes through the draft clause by clause — Regulations 4(a), 5(4), 7(1), 10(5), 10(9), 14(4), 16, 19(2), 22(2), 23, 25, 29(2), 32, 33, 35 and 37, then Form 6B, Appendix III, Appendix V and Appendix VI. Each paragraph states the comment and the "Analysis and decision", quoting the revised wording wherever the draft text was changed.

Recurring themes are parity with CERC's Tariff Regulations, 2019 for return on equity, debt-equity, O&M escalation, late payment surcharge and rebate (p4–5, p11); new OPEX heads covering data, forecasting and software services (p6); a reworked performance-linked incentive and KPI set, with the Commission noting that performance under the old and new KPIs is not comparable (p8–9); and institution-building measures, including a certification-linked incentive for SLDC staff and procedures POSOCO must submit to the Commission (p10, p13). Several POSOCO requests were accepted outright, while most beneficiary objections to charge levels were rejected.

Standard name
SLDC Fees and Charges
Primary topics
SLDC and RLDC fees and charges, Return, financing and working capital, Operating costs and other income

Read with this

Other copies of these documents (1)

One more document belongs here and is not on Voltaic: a draft or notice on a draft.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document