PSERC · Punjab State Electricity Regulatory Commission
Intra-State Open Access (10th Amendment) Regulations, 2022 — Order, 2023
Punjab State Electricity Regulatory Commission (Terms and Conditions for Intra-State Open Access) (10th Amendment) Regulations, 2022
OrderDated 31 May 2023
Read with the Terms and Conditions for Intra-state Open Access Regulations, 2011.
Summary
Summary written by software, from pages 1 to 31 of 44. Check the regulator's original before you rely on it.
This is the Punjab State Electricity Regulatory Commission's order dated 31.05.2023 disposing of the objections and suggestions received on the draft Punjab State Electricity Regulatory Commission (Terms and Conditions for Intra-State Open Access) (10th Amendment) Regulations, 2022 (p1). It records the Commission's reasoned decisions on each proposed change, with PSPCL's and PSTCL's replies, rather than reproducing the amended regulation text itself; these decisions are what carry into the notified amendment.
The background (pp1–2) explains why the amendment is being made: the Ministry of Power's Electricity (Promoting Renewable Energy Through Green Energy Open Access) Rules, 2022, notified on 06.06.2022, whose salient features the order recites — open access for consumers with sanctioned contract demand/load of 100 kW and above, deemed grant of green open access within 15 days, certainty on open access charges including a cap on cross-subsidy surcharge and removal of additional surcharge, a uniform RPO covering green hydrogen/green ammonia, and green certificates issued by distribution licensees. The draft was published in newspapers dated 23.11.2022 and on the Commission's website; 12 objections were received from named objectors and a public hearing was held on 18.01.2023, followed by PSPCL and PSTCL replies dated 18.01.2023, 06.02.2023, 16.02.2023 and 21.02.2023.
Part II takes each amendment in turn. The Regulation 3 definition amendments come first (pp2–7): standby power, admissible drawal, banking, central nodal agency, full open access customer, green energy, green energy open access and its consumer, and partial open access consumer. The Commission accepts clarifications — banking is available to consumers procuring from either intra-state or inter-state projects (p4), and "Partial Open Access Customer" is re-titled "Consumer" to match the DSM Regulations (p7) — while retaining the proposed definition of admissible drawal and of open access customer.
The pages resume at Regulation 28 (pp25–31). The Commission exempts Green Energy Open Access consumers from the requirement in Regulation 28(3) to draw the same open access power for at least twelve consecutive time blocks of 15 minutes, citing the intermittent nature of renewable generation (pp24–25), clarifies that the twelve blocks must be consecutive within a day, and specifies the banking terms under Regulation 28(6) — permitted banked quantum, the banking year, and treatment of unutilised banked energy — adding a proviso that tracks the MoP's Green Energy Open Access Amendment Rules, 2023 (p30).
Read with this
The regulation
Amendments and corrections
- Dated 4 May 2012Intra-State Open Access Regulations, 2011 — Ist Amendment, 2012
- Dated 13 Dec 2012Terms & Conditions for intra-State Open Access Regulations, 2011 — 2nd Amendment, 2012
- Dated 2 Sep 2013Punjab Intra-state Open Access Regulations, 2011 — 3rd Amendment, 2013
- Dated 17 Sep 2014Intra-state Open Access Regulations, 2011 — 4th Amendment, 2014
- Dated 1 Jun 2015Intra-State Open Access Regulations, 2011 — 5th Amendment, 2015
- Dated 21 Jan 2016Intra-state Open Access Regulations, 2011 — 6th Amendment, 2016
- Dated 3 Feb 2016Intra-State Open Access Regulations, 2011 — 7th Amendment, 2016
- Dated 15 Feb 2019Intra-State Open Access Regulations, 2011 — 8th Amendment, 2019
- Dated 17 Oct 2019Intra-State Open Access Regulations, 2011 — 9th Amendment, 2019
- Dated 2 Jun 2023Intra-State Open Access Regulations, 2011 — 10th Amendment, 2023
- Dated 12 Oct 2023Intra-State Open Access (Terms and Conditions) Regulations, 2011 — 11th Amendment, 2023
- Dated 14 Jul 2025Intra-State Open Access Regulations, 2011 — 12th Amendment, 2025
- Dated 12 May 2026Intra-State Open Access Regulations, 2011 — 13th Amendment, 2026
Commencement notices and reasons
- Dated 29 Jun 2011Intra-state Open Access Regulations, 2011 — Statement of Reasons
- Dated 11 Oct 2023Intra-State Open Access (11th Amendment) Regulations, 2023 — Order
- Dated 11 Jul 2025Intra-State Open Access (12th Amendment) Regulations, 2025 — Order
- Dated 12 May 2026Intra-State Open Access (13th Amendment) Regulations, 2026 — Order
Procedures and orders made under it
- Dated 5 Jul 2011Intra-state Open Access Charges Order, 5 July 2011
- Dated 5 Dec 2011Intra-state Open Access Charges — Effective Date Order, 5 December 2011
Voltaic last read PSERC's website for final documents on 26 Nov 2026. A document PSERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.