Skip to content

PSERC · Punjab State Electricity Regulatory Commission

Intra-State Open Access Regulations, 2011 — 7th Amendment, 2016

Punjab State Electricity Regulatory Commission (Terms and Conditions for intra-State Open Access) (7 th Amendment) Regulations, 2016

AmendmentDated 3 Feb 2016No. PSERC/Secy/Regu. 112 dated The 3 rd February, 2016

Amends the Terms and Conditions for Intra-state Open Access Regulations, 2011.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on pserc.punjab.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a two-clause amendment notification issued by the Punjab State Electricity Regulatory Commission on 3 February 2016, changing the Commission's 2011 intra-State Open Access Regulations. It takes effect from publication in the State official Gazette; the Gazette date itself is not printed (p1).

Part 1 names the instrument and fixes commencement (p1).

Part 2 adds a proviso to Regulation 31(1)(c) (p1). A captive co-generation NRSE plant that uses bagasse as fuel, generates power and wheels it for its own use, may bank power for a maximum of six months or 15 days from the close of the sugar mill's cane crushing season, whichever is earlier. The open access customer must give the distribution licensee advance intimation of the season's closure.

Part 3 substitutes Regulation 42 in full (p1–2). Every open access customer must meet its renewable purchase obligation as per the PSERC (Renewable Purchase Obligation and its Compliance) Regulations, 2011, with the minimum percentages prescribed in clause 3(1) of those regulations, and may meet it either by buying renewable electricity in kWh or by buying Renewable Energy Certificates from the power exchange. If a customer fails to comply for the period or year in which it availed open access, the distribution licensee must withhold permission to avail open access for the next period/year until the shortfall is made good.

Standard name
Open Access Regulations
Primary topics
Open access, Renewable purchase obligation (RPO / RCO), Energy banking

Read with this

Voltaic last read PSERC's website for final documents on 26 Nov 2026. A document PSERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on pserc.punjab.gov.in ↗

Report an issue with this document