In the matter of : Determination of charges applicable to the customers seeking Open Access on intra-State transmission and/or distribution system in accordance with Punjab State Electricity Regulatory Commission (Terms and Conditions for intra-State Open Access) Regulations, 2011.

OrderDated 5 Dec 2011

Made under the Terms and Conditions for Intra-state Open Access Regulations, 2011.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on pserc.punjab.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a single-page PSERC order that fixes the date from which the revised intra-state open access charges take effect (p1). The Commission had already determined transmission charges, wheeling charges and cross subsidy surcharge in an order dated 5 July 2011, in line with the revised Open Access Regulations stated to be effective from 1 July 2011 (p1).

Open access customers represented that because PSPCL's public notice on the revised Regulations appeared in newspapers only on 5 July 2011, the revised charges should apply from 7 July 2011 rather than 1 July 2011 (p1).

The Commission accepted the substance of the grievance but not the date: since customers could bid day-ahead on 6 July with knowledge of the revised Regulations, it directs, using Regulation 45 of the Open Access Regulations, that the revised charges apply from 6 July 2011 instead of 1 July 2011 (p1). The order is signed by the Chairperson and both Members and dated 5 December 2011 at Chandigarh (p1). Its practical effect is a short retrospective shift of the charging start date, not a change in the charges themselves.

Standard name
Open Access Regulations
Primary topics
Open access, Open access charges

Read with this

Procedures and orders made under it

Voltaic last read PSERC's website for final documents on 26 Nov 2026. A document PSERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on pserc.punjab.gov.in ↗

Report an issue with this document