CERC · Central Electricity Regulatory Commission
Cross Border Trade of Electricity (First Amendment) Regulations, 2023
Central Electricity Regulatory Commission (Cross Border Trade of Electricity) (First Amendment) Regulations, 2023
AmendmentDated 15 Dec 2023No. 13/2/7/2015-PM/CERC dated 15 th December, 2023
Amends the Cross Border Trade of Electricity Regulations, 2019.
Summary
Summary written by software. Check the regulator's original before you rely on it.
A one-page CERC amendment (p1) to its Cross Border Trade of Electricity Regulations, issued on 15 December 2023 under s.178 read with s.66 of the Electricity Act 2003 and the Ministry of Power's guidelines on the import and export of electricity. It makes two operative changes. First, it inserts a new definition, (tt-A), into Regulation 2 of the Principal Regulations, defining "Settlement Nodal Agency Charge" or "SNA Charge" as the charge payable to the SNA by participating entities located in the neighbouring countries for discharging its mandated functions (p1). Second, it substitutes clause (2) of Regulation 30 so that the SNA may recover an SNA charge of 0.50 paisa (half paisa)/kWh on the energy scheduled, and must formulate a suitable payment security mechanism for the charges it collects (p1). The amendment takes effect from Gazette publication, but the Gazette date is not printed, so the in-force date cannot be fixed from the text (p1).
Read with this
The regulation
- Dated 8 Mar 2019Cross Border Trade of Electricity Regulations, 2019
Amendments and corrections
Commencement notices and reasons
- Dated 20 Mar 2019Cross Border Trade of Electricity Regulations, 2019 — Statement of Reasons
- Dated 15 Dec 2023Cross Border Trade of Electricity Regulations, 2019 — First Amendment, 2023 — Statement of Reasons
- Dated 8 Feb 2026Cross Border Trade of Electricity Regulations, 2019 — Second Amendment, 2025 — Statement of Reasons
Consolidated copies, for reference (1)
- Dated 8 Mar 2019Cross Border Trade of Electricity Regulations, 2019
Other copies of these documents (3)
- Dated 8 Mar 2019Cross Border Trade of Electricity Regulations, 2019
- Dated 15 Dec 2023Cross Border Trade of Electricity (First Amendment) Regulations, 2023
- Dated 9 Dec 2025Cross Border Trade of Electricity Regulations, 2019 — Second Amendment, 2025
Earlier drafts
- Dated 16 Feb 2017Cross Border Trade of Electricity Regulations, 2017 — Draft
- Dated 14 Jan 2016Explanatory memorandum: Guidelines on Cross Border Trade of Electricity, 2016
- Dated 14 Dec 2016Explanatory memorandum: Cross Border Trade of Electricity — Designation of Designated Authority, 2016
- Released with the notice dated 16 Feb 2017Explanatory memorandum: Explanatory Memorandum — Draft Cross Border Trade of Electricity Regulations, 2017
- Dated 16 Feb 2017Public notice: Draft Cross Border Trade of Electricity Regulations, 2017 — Public Notice
- Dated 7 Apr 2017Notice extending the date for comments: Draft Cross Border Trade of Electricity Regulations, 2017 — comment extension notice
- Dated 7 Apr 2017Notice extending the date for comments: Draft Cross Border Trade of Electricity Regulations, 2017 — Public Notice (Extension-II) — comments deadline extended to 17.04.2017
- Dated 28 Aug 2023Cross Border Trade of Electricity (First Amendment) Regulations, 2023
- Dated 28 Aug 2023Explanatory memorandum: Cross-Border Trade of Electricity (First Amendment) Regulations, 2023 — Explanatory Memorandum — Draft
- Dated 28 Aug 2023Public notice: Cross Border Trade of Electricity (First Amendment) Regulations, 2023 — Draft — Public Notice
- Dated 12 Sep 2023Hearing notice: Public hearing notice — Cross-Border Trade of Electricity (First Amendment) Regulations, 2023
- Dated 31 Dec 2024Cross Border Trade of Electricity (Second Amendment) Regulations, 2024 — Draft
- Dated 31 Dec 2024Public notice: Cross Border Trade of Electricity (Second Amendment) Regulations, 2024 — Draft — Public Notice
- Dated 31 Dec 2024Explanatory memorandum: Cross Border Trade of Electricity Regulations, 2019 — Second Amendment, 2024 — Explanatory Memorandum — Draft
- Dated 29 Jan 2025Notice extending the date for comments: Cross Border Trade of Electricity (Second Amendment) Regulations, 2024 — Public Notice, comments deadline extended to 07.02.2025
- Dated 28 Apr 2025Hearing notice: Public hearing notice — Draft Cross Border Trade of Electricity (Second Amendment) Regulations, 2024
3 more documents belong here and are not on Voltaic: 3 drafts or notices on a draft.
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.