State Grid Code (First Amendment) Regulations, 2026 — Statement of Reasons

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (STATE GRID CODE) (FIRST AMENDMENT) REGULATIONS, 2026

Statement of reasonsDated 21 Sep 2026

The commission's reasons for the State Grid Code Regulations, 2020 or one of its amendments.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on merc.gov.in ↗

Summary

Summary written by software, from pages 1 to 25 of 36. Check the regulator's original before you rely on it.

This is the Statement of Reasons for the Maharashtra Electricity Regulatory Commission (State Grid Code) (First Amendment) Regulations, 2026, dated 21 September 2026 (p1). It explains why MERC is reviewing the 2020 State Grid Code (MEGC 2020) and records the public consultation and Commission decisions that underpin the first amendment (p1–3). The background is the CERC's IEGC 2023, its first amendment and tariff amendments, the Ministry of Power's Late Payment Surcharge Rules and their amendment, and CEA advice that State Grid Codes be aligned with IEGC 2023 to facilitate un-requisitioned surplus (URS) sale in power markets (p1–2). The draft amendment was published on 2 August 2025 for comments by 22 August 2025, later extended to 15 September 2025; nine stakeholders responded (p2).

Chapter 1 (pp4–5) covers amendments to Regulation 2 definitions, adding terms relating to ancillary services, area control error, gate closure, GNA, minimum turndown level and SCED/SCUC. The Commission records stakeholder comments on standby meters and VSE/DSM concerns, but makes no change to the draft for these definitions (p4–5).

Chapter 2 (pp5–12) covers Regulation 34 on technical minimum operation and part-load compensation. It sets out the Commission's reasoning on ramp-rate compliance, ex-bus application of technical minimum, readiness for lower technical minimum through the Grid Coordination Committee, VSE treatment, gas-based units, Section 62 versus Section 63 generators, monthly computation versus annual reconciliation, start-stop limits and gain-sharing. The final change to Regulation 34.8.6 aligns post-compensation gain-sharing with the MERC MYT Regulations 2024, replacing the draft's proposed sharing basis (p12).

Chapter 3 (pp12–14) revises Regulation 49.1 applicability of the Scheduling and Despatch Code. It keeps the code applicable to sellers and generators connected to the intra-State transmission system, excluding in-situ captive generators, while extending it to distribution-connected generators that undertake inter-state transactions or sell through open access outside their distribution licensee area; wind and solar remain governed by the MERC F&S Regulations, 2018 (p12–14).

Chapter 4 (pp14–16) amends Regulation 52 on day-ahead scheduling principles. It specifies seller-wise and contract-wise availability forecasts, treatment of captive and open access consumer requirements, SLDC backing down/picking up outside such requirements under the VSE framework, deletion of certain clauses, and RE generator scheduling (p14–16).

Chapter 5 (pp16–23) substitutes Regulation 52.5 with a detailed day-ahead scheduling calendar and despatch procedure. It covers ISGS, sellers, buyers, open access consumers, WRLDC, SLDC, GNA grantees and QCAs; forms under Annexure-10; publication of URS availability; transmission corridor allocation; power exchange bidding windows; SCED/SCUC pilot; and final load-generation balance and despatch schedules (p16–23).

Chapter 6 (pp23–24) amends Regulation 53.2 on revision of schedules following forced outage of ISGS units and transmission constraints, including the timing effect of revisions measured in blocks. Chapter 7 (pp24–25) addresses Regulation 53.3 on SLDC despatch or curtailment instructions under centralised merit order despatch, including schedule revisions and deemed generation.

Standard name
Grid Code
Primary topics
Grid operation and grid code, Scheduling and despatch, Generation tariff

Read with this

The regulation

Amendments and corrections

3 more documents belong here and are not on Voltaic: 1 copy in another language, 1 draft or notice on a draft and 1 draft or notice on a draft not held as English text.

Voltaic last read MERC's website for final documents on 24 Nov 2026 (8 pages) and for drafts on 24 Nov 2026. A document MERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on merc.gov.in ↗

Report an issue with this document