Reactive Energy Accounting Framework for Intra-State Hydro Generating Stations under the State Grid Code Regulations, 2020 — Notification, 2022

Implementation of Reactive Energy Accounting Framework for Intra-State Hydro Electric Generating Stations in terms of the applicable provisions of the MERC (State Grid Code) Regulations, 2020

NotificationDated 9 Mar 2022

Read with the State Grid Code Regulations, 2020.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on merc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

MERC operationalises a framework that the MERC (State Grid Code) Regulations, 2020 had left to a separate commencement date. Pages 1–4 explain why: Regulation 70 of the MYT Regulations, 2019 requires generating stations to inject or absorb reactive energy on MSLDC directions and provides for compensation, with settlement governed by the Grid Code; Regulation 37.16 of the Grid Code required the Commission to notify the date of applicability for intra-State entities (p1). MSLDC reported readiness for only a partial module — condenser-mode reactive energy accounting for hydro generators — and asked to pay MSPGCL's Koyna units from the DSM pool (pp1–2). A DSM Working Group report and MSLDC's draft procedure were placed before the Commission (pp2–4).

The Commission's analysis and ruling (pp4–6) records that Regulation 37.8 allows MSLDC to run hydro units in synchronous condenser mode, and that Annexure-7 of the Grid Code contemplates all TSUs and all generators connected to the InSTS. It nonetheless accepts phased rollout, because grid-level reactive compensation is still inadequate and because kVArh data is missing at locations outside the AMR project (pp3–4). It adopts the Grid Code rate of 13 paise/kVArh escalated by 0.50 paise/kVArh annually as compensation (pp4–6).

The operative direction (p6) starts phase one at 00:00 hrs on Monday, 14 March 2022, covering hydro generators in condenser mode on MSLDC instructions, paid from the State DSM pool account while there are no TSU recoveries; it requires weekly accounts, a review by MSLDC within a year, STU to expedite compensation studies, and all InSTS generating stations to continue following Regulation 37.

The Annexure (pp8–9) is MSLDC's implementation procedure: applicability to hydro stations above 25 MW connected to InSTS, instruction and logging mechanics, weekly 15-minute-block RkVAH meter data from STU, payment priority and pro-rata treatment, DSM portal publication, and a subordination clause to MERC directives and the Grid Code.

Standard name
Grid Code
Primary topics
Energy accounting and settlement, Grid operation and grid code, Power quality

Read with this

The regulation

Amendments and corrections

3 more documents belong here and are not on Voltaic: 1 copy in another language, 1 draft or notice on a draft and 1 draft or notice on a draft not held as English text.

Voltaic last read MERC's website for final documents on 24 Nov 2026 (8 pages) and for drafts on 24 Nov 2026. A document MERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on merc.gov.in ↗

Report an issue with this document