CERC · Central Electricity Regulatory Commission

Terms and Conditions of Tariff (Fourth Amendment) Regulations, 2007

Central Electricity Regulatory Commission (Terms and Conditions of Tariff) (Fourth Amendment) Regulations, 2007

AmendmentDated 28 Dec 2007In force from 7 Jan 2008No. L-7/25(5)/2003-CERC dated 28th December 2007

Replaced by Terms and Conditions of Tariff Regulations, 2009

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Terms and Conditions of Tariff Regulations, 2004.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the CERC's fourth 2007 amendment to its 2004 tariff regulations, issued on 28 December 2007 and commencing at 00:00 hrs on 7 January 2008 (p1). It is a short operative instrument — six regulation changes plus a closing note — not a self-contained code.

Paragraph 2 removes the need to file Forms 5B, 5C and 5D when applying for a provisional tariff (p1). Paragraphs 3 and 5 substitute Regulations 19 and 35 with a single identical clause on sale of infirm power: infirm power is accounted as Unscheduled Interchange and paid from the regional or State UI pool at the applicable frequency-linked UI rate, and the revenue earned must be applied to reduce capital cost rather than be treated as revenue (p1–2).

Paragraphs 4 and 6 substitute Regulations 24(1) and 42(1), defining how UI is computed — actual minus scheduled generation, or actual minus scheduled drawal, for each 15-minute time block — and setting out the frequency-linked UI rate table on which all UI transactions are charged, with a cap for coal/lignite-firing stations and APM-gas-only stations when generation exceeds schedule (p1–4). Regulation 42's replacement also carries the hydro provisions: hydro stations may deviate to follow frequency and inflow so long as they do not game the system or cause a grid constraint, with whole-day net energy deviations trued up through the schedule for Day+3 (p3–4).

Paragraph 7 amends Regulation 45: revisions to declared capability, energy and beneficiary requisitions are allowed only in a contingency and take effect from the sixth time block (p4), and a new clause (xix) states the hydro scheduling rule that daily scheduled energy equals declared available energy, with a worked illustration of the (Day+3) compensation formula (p4). A closing note on p5 lists the principal regulations and the six amendments already made to them.

Standard name
Tariff Regulations
Primary topics
Tariff determination, Deviation settlement (DSM), Scheduling and despatch

Read with this

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.