CERC · Central Electricity Regulatory Commission
Terms and Conditions of Tariff Regulations, 2009
Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2009
RegulationDated 19 Jan 2009In force from 1 Apr 2009No.L-7/145(160)/2008-CERC dated 19th January, 2009
Replaced by Terms and Conditions of Tariff Regulations, 2014
See that regulation for the date it took effect and for anything it keeps in force.
Summary
Summary written by software, from pages 1 to 46 of 63. Check the regulator's original before you rely on it.
The notification is CERC's principal tariff regulation for the 2009-14 control period, made under s.178 of the Electricity Act, 2003 and applying to generating stations, other than non-conventional energy sources, and the inter-State transmission system where CERC determines tariff under s.62 read with s.79 (p1–2). It comes into force on 1.4.2009 and is to remain in force for five years unless reviewed or extended; pre-1.4.2009 projects whose tariff was not finally determined are to have tariff up to 31.3.2009 determined under the 2004 regulations (p1).
Chapter 1 (p1–9) defines the tariff vocabulary — capital cost, COD, cut-off date, change in law, availability measures, useful life and the like — and states the regulation's scope. Chapter 2 (p10–19) sets the procedural and capital-cost machinery: application for tariff under the 2004 procedure regulations and Appendix I, auditor-certified capex, provisional billing for existing projects, truing up after the control period, admission of capital cost after prudence check, initial-spares ceilings, additional capitalisation, R&M and life extension, including a special allowance route for coal/lignite stations, treatment of infirm power, and the debt-equity norm.
Chapter 3 (p20–41) is the computation core. It fixes the components of annual fixed cost; provides the method for return on equity, interest on loan, depreciation, interest on working capital and O&M expenses; gives formulas for secondary fuel oil expense and fuel-price adjustment; and sets out capacity-charge and energy-charge formulas for thermal and hydro stations, transmission charges for ISTS, and treatment of UI. It also permits the Department of Atomic Energy to adopt the same tariff structure for nuclear stations (p36).
Chapter 4 contains operational norms. Regulation 25 makes recovery of capacity, energy and transmission charges dependent on achieving these norms, allows revision of station heat rate norms for relaxed-norm stations, and provides for sharing SFC savings. Regulation 26 begins the thermal norms: NAPAF for different categories of stations, gross station heat rate for existing stations and for new stations achieving COD on or after 1.4.2009, including design heat rate caps. The remaining chapters, regulations and appendices are not available here.
Read with this
Amendments and corrections
- Dated 10 Jun 2009Terms and Conditions of Tariff Regulations, 2009 — Addendum, 2009
- Dated 10 Jun 2009Terms and Conditions of Tariff Regulations, 2009 — Corrigendum, 10 June 2009
- Dated 2 May 2011Terms and Conditions of Tariff Regulations, 2009 — First Amendment, 2011
- Dated 21 Jun 2011Terms and Conditions of Tariff Regulations, 2009 — Second Amendment, 2011
- Dated 31 Dec 2012Terms and Conditions of Tariff (Third Amendment) Regulations, 2012
- Dated 15 Jun 2010Changes some provisions: Sharing of ISTS Charges and Losses Regulations, 2010
- Dated 15 Jun 2010Changes some provisions: Sharing of Inter State Transmission Charges and Losses Regulations, 2010
Commencement notices and reasons
- Dated 3 Feb 2009Terms and Conditions of Tariff Regulations, 2009 — Statement of Objects and Reasons
- Dated 20 Jul 2010Vetting of Capital Cost of Hydro-Electric Projects — Statement of Reasons
- Dated 21 Jun 2011Tariff Second Amendment 2011 — Statement of Reasons
- Date not statedTerms and Conditions of Tariff, 2009 — Third Amendment, 2012 — Statement of Reasons
Procedures and orders made under it
Other copies of these documents (5)
- Dated 19 Jan 2009Terms and Conditions of Tariff Regulations, 2009
- Dated 2 Aug 2010Hydro Electric Project Capital Cost Vetting Guidelines, 2010
- Dated 2 May 2011Terms and Conditions of Tariff (First Amendment) Regulations, 2011
- Dated 21 Jun 2011Terms and Conditions of Tariff Regulations, 2009 — Second Amendment, 2011
- Dated 31 Dec 2012Terms and Conditions of Tariff Regulations, 2009 — Third Amendment, 2012