HPERC · Himachal Pradesh Electricity Regulatory Commission

Renewable Power Purchase Obligation and its Compliance (Second Amendment) Regulations, 2016

Himachal Pradesh Electricity Regulatory Commission (Renewable Power Purchase Obligation and its Compliance) (Second Amendment) Regulations, 2016

AmendmentDated 30 Mar 2016No. HPERC/438 dated the 30th March, 2016

Replaced by Renewable Power Purchase Obligation and its Compliance Regulations, 2023

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Renewable Power Purchase Obligation and its Compliance Regulations, 2010.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on hperc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the second amendment to HPERC's 2010 Renewable Power Purchase Obligation (RPPO) regulations, issued on 30 March 2016 and taking effect from the date of Rajpatra publication (p1). Pages 1-2 carry the operative text; pages 3-4 carry the Commission's Statement of Reasons and order approving the draft.

The amendment rewrites three provisions of the 2010 regulations. Regulation 3, on applicability, is substituted wholesale, re-listing who is an obligated entity: the distribution licensee; any person consuming conventional-source electricity through open access third-party sale; and conventional captive generating plants, split between those used purely for standby/emergency back-up and those meeting normal requirements (p1). Regulation 7(1) is amended by omitting the sentence that barred carry-forward of credit for excess renewable power purchase, so excess RE purchase can now be adjusted in the ensuing year(s) (p2, p4). Regulation 8(2) is substituted with a new compliance-reporting regime for obligated entities other than the distribution licensee — quarterly submissions and an annual consolidated report on stated deadlines (p2).

The Statement of Reasons explains the trigger: HPSEBL supplies 80% green energy from hydro sources, smaller standby captive plants have negligible RPPO, and MERC and GERC approaches are cited as comparators (p3). It records the draft publication, newspaper consultation on 10 March 2016, and that no comments or suggestions were received (p4).

Standard name
RPO Regulations
Primary topics
Renewable purchase obligation (RPO / RCO), Compliance and reporting, Captive status

Read with this

Proposed changes (drafts with no final yet)

3 more documents belong here and are not on Voltaic: 1 amendment, 1 commencement notice or statement of reasons and 1 procedure or order made under it.

Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.