Skip to content

HPERC · Himachal Pradesh Electricity Regulatory Commission

Fixation of Fees and Charges for Accreditation of Renewable Energy Generation Project Order, 2015

Himachal Pradesh Electricity Regulatory Commission (Fixation of Fees and Charges for Accreditation of Renewable Energy Generation Project) Order, 2015

OrderDated 14 Aug 2015No.-HPERC/438(TA) dated 14.08.2015

Replaced by Renewable Power Purchase Obligation and its Compliance Regulations, 2023

See that regulation for the date it took effect and for anything it keeps in force.

Made under the Renewable Power Purchase Obligation and its Compliance Regulations, 2010.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on hperc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a one-page HPERC order, issued 14 August 2015, that fixes what a renewable energy generator must pay the State Agency to get its project accredited under the Commission's Renewable Power Purchase Obligation framework. The order contains only a short-title clause and a single fee paragraph (p1).

Paragraph 2 sets four charges, each expressed per application: a non-refundable, one-time application processing fee payable with the application (p1); a one-time accreditation charge payable on grant of accreditation (p1); an annual accreditation charge with a fixed payment deadline of 10 April each year (p1); and a revalidation/extension charge payable when an existing accreditation is renewed at the end of its validity, which the order puts at five years or such other period as the Commission may determine (p1). Taxes and duties on these amounts follow prevailing norms (p1).

No Gazette publication date, commencement clause or validity period is printed.

Standard name
RPO Regulations

Read with this

Proposed changes (drafts with no final yet)

3 more documents belong here and are not on Voltaic: 1 amendment, 1 commencement notice or statement of reasons and 1 procedure or order made under it.

Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on hperc.org ↗

Report an issue with this document