Renewable Power Purchase Obligation and its Compliance Regulations, 2010 — Sixth Amendment, 2020

Himachal Pradesh Electricity Regulatory Commission (Renewable Power Purchase Obligation and its Compliance) (Sixth Amendment) Regulations, 2020

AmendmentDated 5 Feb 2020No. HPERC/438 dated the 5th February, 2020

Replaced by Renewable Power Purchase Obligation and its Compliance Regulations, 2023

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Renewable Power Purchase Obligation and its Compliance Regulations, 2010.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on hperc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

These are HPERC's Sixth Amendment Regulations, 2020, issued at Shimla on 5 February 2020 under No. HPERC/438 (p1). They amend the Himachal Pradesh Electricity Regulatory Commission (Renewable Power Purchase Obligation and its Compliance) Regulations, 2010 (the "RPO Compliance Regulations, 2010") and come into force from the date of publication in the Rajpatra, Himachal Pradesh; the Gazette date itself is not printed (p1).

The operative part is Regulation 2. It inserts a saving note below the RPPO table in regulation 4(1), preserving the Commission's RPO trajectory and any omitted or revised provisions from time to time, and replaces the table label "distribution licensee" with "distribution licensee/obligated entity" (p1). It substitutes regulation 4(2), extending RPPO to any person or consumer who consumes power from generation or purchase, including open access, but not as a consumer of a distribution licensee or by drawl from a captive generating plant. The substituted sub-regulation sets how such an obligated entity's consumption is computed: it includes purchased or generated electricity and power bought under the REC mechanism, plus transmission and distribution losses; out-of-State purchases are measured at the State periphery, and in-State generation at the generating bus bar. It also provides that non-distribution-licensee consumption is deemed non-hydro unless the entity proves hydro sourcing to the State Agency (p1–2).

A new regulation 4(2A) applies RPPO to captive generating plant drawl at rates specified in the Schedule, but only for captive plants covered by regulation 3(c) and 3(d) of the 2010 regulations (p2). The Schedule sets minimum Renewable Power Purchase Obligation percentages for captive consumption by reference to the year the plant's original capacity was commissioned or augmented, split into non-solar, solar and total, and adds footnotes on the consumption base, compliance-relaxation thresholds and treatment of capacity augmented after 31.03.2016 (p2).

Standard name
RPO Regulations
Primary topics
Renewable purchase obligation (RPO / RCO)

Read with this

Proposed changes (drafts with no final yet)

3 more documents belong here and are not on Voltaic: 1 amendment, 1 commencement notice or statement of reasons and 1 procedure or order made under it.

Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.