Skip to content

MERC · Maharashtra Electricity Regulatory Commission

Distribution and Transmission Open Access Regulations, 2016 — First Amendment, 2019 — Statement of Reasons

Maharashtra Electricity Regulatory Commission (Distribution Open Access) (First Amendment) Regulations, 2019 And Maharashtra Electricity Regulatory Commission (Transmission Open Access) (First Amendment) Regulations, 2019 STATEMENT OF REASONS

Statement of reasonsDated 3 Jun 2019

The commission's reasons for the Distribution Open Access Regulations, 2016 or one of its amendments.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on merc.gov.in ↗

Summary

Summary written by software, from pages 1 to 25 of 54. Check the regulator's original before you rely on it.

The document is MERC's Statement of Reasons for the First Amendment to its 2016 Distribution Open Access (DOA) and Transmission Open Access (TOA) Regulations, dated 3 June 2019 (p1). It explains why the Commission reviewed the 2016 open-access framework, citing CERC's 2017 connectivity/open-access regulations, a Ministry of Power consultation paper, stakeholder representations and adjudication difficulties (p1). It records the public consultation: draft amendments published on 11 March 2019, objections due 1 April 2019 and extended to 8 April 2019, with 113 responses (p2).

The main body is an issue-by-issue account of comments received and the Commission's analysis and final decision. Issues 1–5 deal with definitions, eligibility and capacity conditions: contract demand, LTOA/MTOA/time block; the 1 MVA eligibility threshold; limits on OA capacity for partial and full OA consumers, with an exemption for renewable-energy OA; threshold-demand penalties; and simultaneous rooftop solar with OA under gross metering (pp2–11). Issue 6 covers revision of contract demand, retaining consumer choice under the Supply Code and Standards of Performance but specifying notional contract demand and incremental demand charges for non-RE OA (pp11–15). Issues 7–8 link the DOA Regulations to the 2019 DSM Regulations and the 2018 solar/wind F&S Regulations and deal with infirm power injection before the DSM effective date (pp15–20). Issue 9 sets the duration categories for LTOA, MTOA and STOA and removes the MTOA proviso (pp20–21). Issue 10 mandates online processing of STOA/MTOA applications and fees, with portal and GST-invoice timelines (pp21–23). Issue 11 sets minimum scheduling conditions for day-ahead OA (pp23–24). Issue 12 begins on repeated STOA roll-over and transmission charges.

Standard name
Open Access Regulations
Primary topics
Open access, Open access charges, Deviation settlement (DSM)

Read with this

Read with this: Distribution Open Access Regulations, 2016

The regulation

Other copies of these documents (1)

8 more documents belong here and are not on Voltaic: 5 drafts or notices on a draft, 2 drafts or notices on a draft not held as English text and 1 copy in another language.

It is also read with: Transmission Open Access Regulations, 2016

The commission's reasons for the Transmission Open Access Regulations, 2016 or one of its amendments.

The regulation

Amendments and corrections

Commencement notices and reasons

Other copies of these documents (1)

Earlier drafts

2 more documents belong here and are not on Voltaic: 1 copy in another language and 1 draft or notice on a draft not held as English text.

Voltaic last read MERC's website for final documents on 24 Nov 2026 (8 pages) and for drafts on 24 Nov 2026. A document MERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on merc.gov.in ↗

Report an issue with this document