Guidelines for Vetting of Capital Cost of Hydro Electric Projects by Designated Independent Agencies/Experts, 2010

Guidelines for vetting of the capital cost of hydro electric projects by Designated Independent Agencies or Institutions or Experts and other related matters

GuidelinesDated 2 Aug 2010No. L-1/50/2010-CERC dated 2nd August 2010

Replaced by Terms and Conditions of Tariff Regulations, 2014

See that regulation for the date it took effect and for anything it keeps in force.

Made under the Terms and Conditions of Tariff Regulations, 2009.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

CERC's notification of 2 August 2010 (No. L-1/50/2010-CERC) builds a vetting regime for the capital cost of hydro-electric projects whose tariffs the Commission sets. It is issued under a specific window in the CERC (Terms and Conditions of Tariff) Regulations, 2009 — the third proviso to Regulation 7(2) — which lets the Commission issue guidelines for independent vetting of hydro capital cost (p1).

Paras 1 to 4 set the frame: title, applicability, objectives and definitions (pp1–3). The guidelines bind Designated Independent Agencies/Experts and generating companies that are central generators or have a composite scheme selling power in more than one State — i.e. those inside CERC's tariff jurisdiction (pp1–2). They take effect on Gazette publication; no Gazette date is printed (p2).

Para 5 (pp3–4) governs selection: the agency is drawn from a panel published on the Commission's website and picked through a transparent multi-bid process at the lowest quotation, with an exception where only one bid arrives, and under a conflict-of-interest bar with a look-back period. Para 6 (p5) caps consultancy charges, with an extra slab where geological surprises delay commissioning.

Para 7 (pp5–7) is the technical core — the appraisal factors (site, geology, hydrology, river-basin development, design options, cost estimates, funding, schedule, geological surprises, time and cost overrun), the split of overrun into attributable and non-attributable, submission deadlines, confidentiality, and a duty to appear before the Commission at the tariff hearing. Para 8 (pp8–10) places obligations on the generating company: DPR preparation and contents, adherence to CEA/CWC guidelines, milestone scheduling, prompt disclosure of design or cost changes, supply of tender documents, and filing the appraisal with the tariff petition. The Commission then considers the vetted cost when determining tariff.

Standard name
Tariff Regulations
Primary topics
Capital cost and investment, Generation tariff

Read with this

The regulation

Other copies of these documents (5)

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.