Hydro Electric Project Capital Cost Vetting Guidelines, 2010

Guidelines for vetting of the capital cost of hydro electric projects by Designated Independent Agencies or Institutions or Experts and other related matters

Gazette copyDated 2 Aug 2010Published in the Gazette 7 Aug 2010No. L-1/50/2010-CERC dated the 2nd August, 2010

Replaced by Terms and Conditions of Tariff Regulations, 2014

See that regulation for the date it took effect and for anything it keeps in force.

A Gazette copy of the Terms and Conditions of Tariff Regulations, 2009 or of one of its amendments.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a CERC notification publishing guidelines for how the capital cost of hydro-electric projects is to be vetted by independent agencies or experts before CERC determines the project's tariff. The Gazette masthead is dated 7 August 2010 (p1); the notification itself is dated 2 August 2010 and numbered L-1/50/2010-CERC (p8). The guidelines are issued because the third proviso to Regulation 7(2) of the CERC (Terms and Conditions of Tariff) Regulations, 2009 allows the Commission to issue such guidelines (p8).

Sections 2–4 set the title, applicability and objectives. They apply to designated independent agencies/experts and to central generating companies or generating companies with a composite scheme for sale of power in more than one State whose hydro project tariffs are determined by CERC (p8–9). They come into force from the date of notification in the Official Gazette (p9). The objectives are to describe roles, information exchange, scope and stages of vetting, and the vetting procedure for tariff purposes (p9). Definitions cover the designated agency/expert and the generating company, with other terms read from the Electricity Act 2003 or the 2009 Tariff Regulations (p9–10).

Sections 5–6 deal with selection and fees. CERC publishes a panel of agencies/experts and may add or delete names (p10). The generating company selects from the panel, invites bids from two or more and picks the lowest quotation, with a single-bid exception and conflict-of-interest rules; it may change agency in specified circumstances with prior intimation (p10–11). Consultancy charges are capped at the lower of a percentage of capital cost excluding IDC and financing charges, or a fixed rupee amount, with a pro-rata addition for geological surprises (p12).

Sections 7–8 allocate responsibilities. The independent agency appraises capital cost against an enumerated list of technical, geological, hydrological, environmental, resettlement, cost, funding and schedule factors, reports attributable and non-attributable cost overruns, and submits its appraisal within stated timelines, including provisos for design changes, ongoing projects and natural calamities; its monitoring is limited to cost appraisal and it must appear before CERC in tariff hearings (p12–14). The generating company prepares the DPR per CEA/CWC guidelines, includes a checklist and clearances, sets out a PERT/CPM schedule, updates changes, furnishes tender and award information, and files the agency's appraisal with its tariff petition; the vetted capital cost is then considered by CERC under the 2009 Tariff Regulations (p15–17).

Standard name
Tariff Regulations
Primary topics
Capital cost and investment, Generation tariff

Read with this

The regulation

Other copies of these documents (4)

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document