Skip to content

CERC · Central Electricity Regulatory Commission

Terms and Conditions of Tariff Regulations, 2009 — Statement of Objects and Reasons

CERC (Terms and Conditions of Tariff) Regulations, 2009

Statement of reasonsDated 3 Feb 2009

Replaced by Terms and Conditions of Tariff Regulations, 2014

See that regulation for the date it took effect and for anything it keeps in force.

The commission's reasons for the Terms and Conditions of Tariff Regulations, 2009 or one of its amendments.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software, from pages 1 to 37 of 165. Check the regulator's original before you rely on it.

Pages 1–37 are the opening of the Statement of Objects and Reasons (SOR) for the CERC (Terms and Conditions of Tariff) Regulations, 2009, covering the Commission’s reasoning behind the regulations for the tariff period 1.4.2009–31.3.2014 (p2). It records the draft regulations issued by public notice on 29 August 2008, the public hearing on 3–4 November 2008, stakeholder comments, and the Commission’s findings (p2).

The SOR first sets out the Commission’s statutory mandate under the Electricity Act, 2003 to regulate tariff of central generating companies and inter-State transmission, and the requirement of previous publication (p1–2). It then deals with preliminary objections from UPPCL and MPPTCL that the Commission should first specify a procedure regulation under s.62(5) for calculating expected revenues. The Commission rejects the objection and says the scope of s.62(5) is limited to specifying formats for calculating expected revenue, which it will provide (p2–7).

The scope section states that the regulations apply where tariff is determined under s.62 read with s.79, but excludes generating stations based on non-conventional energy sources, for which a separate regulation is planned (p7). The definitions section explains changes on auditor, the replacement of “actually incurred” with “expenditure incurred”, and useful life by asset category from COD (p7–10).

The middle sections explain application and truing-up changes. Existing projects are to file based on admitted capital cost as on 31.3.2009; pending final tariff, they continue billing the tariff applicable on 31.3.2009, with differences settled at SBI PLR-linked simple interest (p10–11). Capital-cost truing up is shifted to the petition for the next tariff period, covering expenditure up to 31.03.2014, with an application deadline (p12–13).

The SOR then discusses capital cost and additional capitalisation: treatment of equity above 30% as normative loan, interest during construction and foreign-exchange variation on the normative loan, retention of initial-spares norms, admissibility of projected and actual additional capital expenditure, and special provisions for hydro stations, transmission systems and minor assets (p13–22). It explains the renovation-and-modernisation versus special-allowance option for stations beyond useful life, including the conditions attached and the annual escalation (p22–25).

Finally, it records the decision to keep existing-project debt-equity ratios unchanged while applying 70:30 to new projects, the move to pre-tax return on equity with an additional incentive for timely completion keyed to Appendix II timelines, and the shift from post-tax to pre-tax tax pass-through limited to the equity component (p25–37).

Standard name
Tariff Regulations
Primary topics
Tariff determination, Generation tariff, Transmission tariff

Read with this

The regulation

Other copies of these documents (5)

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document