HPERC · Himachal Pradesh Electricity Regulatory Commission
Transmission Tariff Regulations, 2011 — First Amendment, 2013
Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Transmission Tariff) (First Amendment) Regulations, 2013
AmendmentDated 1 Nov 2013No. HPERC/F(5)(3)(1)(Trans).- dated 1stNovember, 2013
Replaced by Transmission Tariff Regulations, 2023
See that regulation for the date it took effect and for anything it keeps in force.
Amends the Transmission Tariff Regulations, 2011.
Saving clause of the regulation that replaces it: “Notwithstanding such repeal- (a) anything done or any action taken or purported to have been done or taken under the repealed Regulations shall, in so far as it is not inconsistent with the provisions of these Regulations, be deemed to have been done or taken under the corresponding provisions of these Regulations;”
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the First Amendment to the HPERC (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011, issued by the Himachal Pradesh Electricity Regulatory Commission at Shimla on 1 November 2013 (p1). It was made ahead of the Commission's exercise to determine transmission tariff for the control period starting 1 April 2014, and it comes into force on Rajpatra publication — a date the text does not print — and applies to tariff orders for control periods commencing 1 April 2014 and thereafter (p1).
The amendment rewrites fifteen regulations of the 2011 parent. It redefines the tariff vocabulary — "existing project" and a new "mid-term performance review" — and widens the voltage band that defines the transmission system to high and extra high voltage lines of 33 kV and above (p1). Regulation 7 is changed so the capital investment plan is set with the distribution licensee also in view, and so that approved capex and capitalisation are not revisited mid-period except at the mid-term review and end-of-period true up (p2). Regulation 10 on true up is replaced wholesale, fixing when true ups happen and the principles applied, including that O&M surpluses and deficits stay with the licensee and that force majeure, change-in-law and tax effects pass through as ARR charge or rebate (p2–3).
Regulation 13 gains a new sub-regulation (1-a) on O&M norms — how employee, R&M and A&G trajectories are to be proposed, what is excluded, and what is allowed over and above the norm — together with a replaced sub-regulation (3) giving the O&M expense formula and the definition of each term in it (p3–5). Further amendments cover capital cost treatment for existing projects (reg 14), disallowance of minor asset purchases after the cut-off date (reg 16), grossing up of return on equity and a changed illustration figure (reg 19), the switch of working-capital and loan interest benchmarks to SBI Base Rate plus basis points (regs 22, 26), a substituted safety-standards regulation requiring a safety manual and CEA compliance (reg 30), and a proviso letting the Commission change transmission pricing mid-period to follow CERC's framework (reg 31) (p5–6).
Filing and review machinery is reworked: business plan and tariff application timing (regs 37, 38), and a substituted regulation 39 setting out the scope of the mid-term performance review and the comprehensive review at the end of the control period, including a comparison against approved forecasts and possible revision of principles for the next period (p6–7). Regulation 43's proviso date is replaced with "the end of previous control period" (p8).
Read with this
The regulation
- Dated 1 Apr 2011Transmission Tariff Regulations, 2011
Amendments and corrections
Commencement notices and reasons
Procedures and orders made under it
- Dated 2 Apr 2011Multi Year Control Period Notification for the Transmission Licensee, 2011
- Dated 2 Apr 2011Formats for Multi Year Tariff Filings by the Transmission Licensee Order, 2011
- Dated 1 Nov 2013Formats for Multi Year Tariff Filings by the Transmission Licensee Order, 2013
- Dated 30 Nov 2016Transmission Licensee ARR & Tariff Filing Formats
- Dated 30 Nov 2016Transmission Licensee ARR & Tariff Filing Formats
- Dated 21 May 2022Himachal Pradesh Intra-State Transmission TBCB Threshold Order, 2022
- Dated 21 May 2022Intra-State Transmission TBCB Threshold Notification, Himachal Pradesh, 2022
- Dated 2 Dec 2023Fixation of Multiyear Control Period, 2023
Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.