Transmission Tariff Regulations, 2011 — Third Amendment, 2023

Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Transmission Tariff) (Third Amendment) Regulations, 2023

AmendmentDated 2 Jun 2023In force from 21 May 2022No. HPERC-F(1)-3/2018 dated the 2nd June, 2023

Replaced by Transmission Tariff Regulations, 2023

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Transmission Tariff Regulations, 2011.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal- (a) anything done or any action taken or purported to have been done or taken under the repealed Regulations shall, in so far as it is not inconsistent with the provisions of these Regulations, be deemed to have been done or taken under the corresponding provisions of these Regulations;”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on hperc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a short amendment notification from the Himachal Pradesh Electricity Regulatory Commission, dated Shimla, 2 June 2023 (p1). It is the Third Amendment to the HPERC (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011, and it does one substantive thing: it replaces Regulation 2(2) of those regulations (p2).

The preamble sets out why. Clause 5.3 of the National Tariff Policy, 2016 requires intra-state transmission to be developed through competitive bidding above a threshold the State Commission itself decides, and HPERC notified that threshold on 21 May 2022 (p1).

The substituted sub-regulation therefore provides that where tariff has been determined through transparent bidding, the Commission adopts it; and it adds two provisos. All intra-state transmission projects — a transmission line, a sub-station, or both as a package — above the threshold limit of Rs. 45 Crore must go through Tariff Based Competitive Bidding under State Government guidelines. Where the State Government or the Transmission Licensee wants a cost-plus route instead for a project above the threshold, it must obtain the Commission's prior approval (p2).

Regulation 1 gives the amendment retrospective effect from 21 May 2022, matching the threshold notification (p2). The notification is signed by the Commission's Secretary (p2).

Standard name
Transmission Tariff Regulations
Primary topics
Transmission tariff, Competitive bidding

Read with this

The regulation

Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.