Skip to content

HPERC · Himachal Pradesh Electricity Regulatory Commission

Formats for Multi Year Tariff Filings by the Transmission Licensee Order, 2013

Himachal Pradesh Electricity Regulatory Commission (Formats for Multi Year Tariff Filings by the Transmission Licensee) Order, 2013

OrderDated 1 Nov 2013No. HPERC/F(5)(3)(1)(Trans) dated 1st November, 2013

Replaced by Transmission Tariff Regulations, 2023

See that regulation for the date it took effect and for anything it keeps in force.

Made under the Transmission Tariff Regulations, 2011.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal- (a) anything done or any action taken or purported to have been done or taken under the repealed Regulations shall, in so far as it is not inconsistent with the provisions of these Regulations, be deemed to have been done or taken under the corresponding provisions of these Regulations;”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on hperc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a one-page operative order with a format index annexure, issued by HPERC on 1 November 2013, that revises the forms a transmission licensee must use when filing its Multi Year Tariff petition (p1). It replaces the earlier filing formats and applies to the control period beginning 1 April 2014 and thereafter (p1).

The Order body is short: paragraph 1 gives the short title and says the Order takes effect on publication in the Himachal Pradesh Rajpatra; paragraph 2 defines 'Act', 'Annexure', 'Form' and 'regulations' and imports definitions from the Act for everything else; paragraph 3 requires MYT filings by the transmission licensee to be made in the annexed Forms, hosted on the HPERC website, and permits those Forms to be used with such modifications as the circumstances of each case require, with any uncovered contingency to be filed on a Form approved by the Commission (p1).

The Annexure is an index of regulatory compliance formats grouped into three blocks (p2): summary formats covering annual revenue requirement, return on equity, energy balance and details of transmission lines and substations; financial formats covering O&M, employee and A&G costs, fixed assets and depreciation, the several loan and interest categories, capitalisation, capital expenditure, work in progress, working capital, admitted capital cost, financial package to COD, additional capitalisation and share capital/reserves; and quality-of-service formats covering system losses, metering status, voltage profile, frequency excursions, HT feeder tripping outages, transformer failure, major system disturbances, electrical accidents and peak demand (p2). The actual contents of the individual Forms are not reproduced in this document — only their titles are indexed (p2).

Standard name
Transmission Tariff Regulations
Primary topics
Transmission tariff, ARR and true-up, Capital cost and investment

Read with this

The regulation

Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on hperc.org ↗

Report an issue with this document