HPERC · Himachal Pradesh Electricity Regulatory Commission

Rooftop Solar PV Grid Interactive System based on Net Metering Order, 2019

Himachal Pradesh Electricity Regulatory Commission (Rooftop Solar PV Grid Interactive System based on Net Metering) Order, 2019

OrderDated 30 Mar 2019No. HPERC-H(1)-11/2017 dated 30th March, 2019

Made under the Rooftop Solar PV Grid Interactive Systems based on Net Metering Regulations, 2015.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on hperc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a short HPERC notification, dated 30 March 2019 and numbered HPERC-H(1)-11/2017, that fixes the rate at which Himachal Pradesh distribution licensees must pay domestic consumers for rooftop solar energy credits left unadjusted at the end of a settlement period (p1). It is a single-purpose tariff order, not an amendment to the net-metering regulations; it is made under Section 181 and Regulation 10(9) of the HPERC (Rooftop Solar PV Grid Interactive System based on Net Metering) Regulations, 2015 (p1).

The short title clause names it the HPERC (Rooftop Solar PV Grid Interactive System based on Net Metering) Order, 2019 (p1). Clause 2 narrows who it reaches: only domestic supply consumers whose Letter of Approval for a net-metered rooftop system was issued after 15 November 2018 and who then installed it, and only grid-connected systems using crystalline silicon, thin film or other technology approved by the Ministry of New and Renewable Energy (p1).

Clause 3 carries the substance. The licensee must compute, for each settlement period, a per-kWh credit rate equal to a fixed share of the weighted average rate at which it bought power from in-State ground-mounted solar PV plants up to 5 MW during the calendar year ending 31 December that falls in that settlement period (p1). The rate is expressly subject to the 2015 Regulations and any orders issued under them (p1–2). Payment covers credits remaining unadjusted at settlement over the system's useful life (p2). The order also imposes a disclosure duty: the licensee must work out the weighted average for each calendar year and publish the rate payable for each completed settlement period on its website by the 15th of February each year (p2). The order is signed by the Secretary at Shimla and says nothing about commencement or expiry.

Standard name
Net Metering and Rooftop Solar
Primary topics
Net metering, Renewable energy tariff

Read with this

Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.